You want to maintain key figure values for a new attribute and value combination, using SAP IBP, add-infor Microsoft Excel, and you are receiving an error related to missing combinations. How can you resolve this problem? Note: There are 2 correct answers to this question
Answer : A, C
You need to use your resource cost effectively with a certain minimum use, even if it means producing more than demand. Which solutions would apply to this scenario? Note: There are 2 correct answers to this question.
Answer : A, C
What are the relevant use cases for helper key figures? Note: There are 2 correct answers to this questions.
Answer : A, D
What are some of the prerequisites for configuring a planning area that results in a successful consistency check? Note: There are 2 correct answers to this question.
Answer : B, D
What are the possible ways that an attribute intended for use as an attribute as a key figure can be created and assigned? Note: There are 2 correct answers to this question.
Answer : C, D
You have set up a planning area, and data is now available. You adjust the necessary time profile settings and run a consistency check Which settings can you change and still run a successful consistency check? Note: There are 2 correct answers to this question
Answer : C, D
What are the S&OP operator (optimizer) parameters associated with demand fair share?
Answer : B