AACE International AACE-PSP Planning & Scheduling Professional (PSP) Exam Practice Test

Page: 1 / 14
Total 163 questions
Question 1

Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?



Answer : A


Question 2

Who will receive the most benefit from a master schedule of the Spring Highway project?



Answer : D


Question 3

Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?



Answer : A


Question 4

Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?



Answer : C


Question 5

Which of the following parties is NOT a stakeholder of the Spring Highway project?



Answer : A


Question 6

Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?



Answer : C


Question 7

In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?



Answer : A


Page:    1 / 14   
Total 163 questions