Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?
Answer : A
Who will receive the most benefit from a master schedule of the Spring Highway project?
Answer : D
Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?
Answer : A
Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?
Answer : C
Which of the following parties is NOT a stakeholder of the Spring Highway project?
Answer : A
Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?
Answer : C
In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?
Answer : A