AACE International Planning & Scheduling Professional (PSP) AACE-PSP Exam Practice Test

Page: 1 / 14
Total 163 questions
Question 1

Which of the following are NOT normally included in the project scope statement, either directly or by reference?



Answer : C


Question 2

Which activity is drawn in the incorrect position?



Answer : C


Question 3

Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?



Answer : A


Question 4

Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.



Answer : C


Question 5

The amount of time that an activity can be delayed from its early start date without delaying project completion is called:



Answer : C


Question 6

In its simplest form, what is the main drawback of critical path method scheduling?



Answer : B


Question 7

Determine the correct formula and date for the late finish for Activity 9004.



Answer : A


Page:    1 / 14   
Total 163 questions