AACE International Planning & Scheduling Professional (PSP) AACE-PSP Exam Questions

Page: 1 / 14
Total 216 questions
Question 1

Is activity 7001 pictured correctly in the precedence diagram?



Answer : D

Activity Details (7001 - 'Permanent Roads'):

Duration: 48 days in the Normal schedule.

Precedence Diagram Information: The schedule correctly reflects the logic and relationships as FS (Finish-to-Start) with successors.

Total Float and Dates Review:

No discrepancies are provided in the diagram.

Early Start (ES) and Early Finish (EF) align with the planned duration and dependencies.

Validation:

Total float is not specified as incorrect.

Early Finish dates, while not explicitly displayed, do not contradict the sequence.

Start-to-Start and Finish-to-Finish relationships are correctly oriented.

Conclusion: The activity is correctly represented with a duration of 48 days.


Question 2

Before the work begins, the contractor considers crashing the schedule. How much would the crashed general conditions have to be reduced to break even with the normal cost budget?



Answer : B


Question 3

The project goals_________.



Answer : C


Question 4

The primary determination of schedule detail is:



Answer : B


Question 5

Each of the following accurately describes total float in a schedule EXCEPT:



Answer : C

Total float measures the flexibility in an activity's timing within a schedule. It is defined as the amount of time an activity can be delayed without affecting the project's overall completion date or the completion date of any of its successors.

Option A, B, and D accurately describe total float: it is calculated as the difference between early and late start/finish dates, can be positive or negative, and is associated with project completion.

Option C describes free float, not total float, and thus is incorrect.


Question 6

In a "crashed" schedule, which is a chain of activities that precede activity 2004?



Answer : A

Crashed Schedule Predecessors to Activity 2004:

Activity 2004 (River Diversion to Pipeline) depends on completion of:

1001 (Preliminary Civil Work).

2001 (River Diversion Stage 1).

2002 (River Diversion Stage 2).

2003 (River Diversion Dam).

Exclusion of Other Activities:

Activity 2007 is not part of the crashed schedule's direct predecessor chain.

Other options include duplicated or incorrect entries.

PSP Study Guide Reference: Logical sequence analysis confirms these predecessors (Ref: PSP Study Guide, Chapter 2A: Activity Sequencing and Critical Path Analysis).


Question 7

Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that



Answer : A

Retaining existing logic means preserving the original relationships and dependencies defined in the schedule. Even if progress is recorded out of sequence, calculations adhere to the pre-established logic unless explicitly changed.

Option B reflects adjustments for out-of-sequence progress but contradicts the original logic requirement.

Option C imposes restrictions that do not align with typical CPM calculations.

Option D is incorrect as the concept exists.

The PSP Study Guide discusses the importance of maintaining logic integrity in CPM scheduling.


Page:    1 / 14   
Total 216 questions