AACE International Planning & Scheduling Professional (PSP) Exam Practice Test

Page: 1 / 14
Total 120 questions
Question 1

Which of the following is NOT true?



Answer : A


Question 2

At the end of month one, did the delay to the parking structure foundation delay the project?



Answer : B


Question 3

If all other work proceeds according to the Baseline plan, how many times will the critical path change?



Answer : C


Question 4

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?



Answer : C


Question 5

If Activity E's duration changes to 4 months, what is the overall duration of the project.



Answer : B


Question 6

Activity C is a



Answer : D


Question 7

Why does activity 11001 not show successor activities?



Answer : D


Page:    1 / 14   
Total 120 questions