How many entities/subcontractors should a scheduled activity cover?
Answer : C
Activity 2003 started during the current reporting period and proceeded as planned with the normal schedule. If the remaining duration at the end of this period is ten workdays, then what is the earned value assignable to Activity 2003 in the pay estimate for this reporting period?
Answer : B
The Organizational Breakdown Structure (OBS) is a hierarchical structure that does NOT include which of the following:
Answer : B
Project Life Cycle Phases do NOT include the following item:
Answer : B
You are the project manager of the AHQ project. This project is scheduled to last for six months and will require S345.000 to complete. If the project completes earlier than scheduled your organization will receive a bonus of S5 000 per day of early completion Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?
Answer : C
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that
Answer : A
Retaining existing logic means preserving the original relationships and dependencies defined in the schedule. Even if progress is recorded out of sequence, calculations adhere to the pre-established logic unless explicitly changed.
Option B reflects adjustments for out-of-sequence progress but contradicts the original logic requirement.
Option C imposes restrictions that do not align with typical CPM calculations.
Option D is incorrect as the concept exists.
The PSP Study Guide discusses the importance of maintaining logic integrity in CPM scheduling.
When are KPIs defined?
Answer : A