AACE International AACE-PSP Planning & Scheduling Professional (PSP) Exam Practice Test

Page: 1 / 14
Total 163 questions
Question 1

What activities are concurrent to Activity 2001 in the "normal" schedule?



Answer : A


Question 2

The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?



Answer : D


Question 3

If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using



Answer : C


Question 4

What is the result of a forward pass calculation?



Answer : B


Question 5

By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:



Answer : C


Question 6

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?



Answer : A


Question 7

Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?



Answer : B


Page:    1 / 14   
Total 163 questions