AACE International Planning & Scheduling Professional (PSP) Exam Practice Test

Page: 1 / 14
Total 120 questions
Question 1

What is the cycle time?



Answer : B


Question 2

How could the structural steel drawing delay have been prevented?



Answer : A


Question 3

What problems can a soils engineer deal with on a project?



Answer : B


Question 4

What owner action could have mitigated the late completion of the project?



Answer : C


Question 5

For which of these delays should an owner grant a time extension?



Answer : C


Question 6

In a "crashed" schedule, which is a chain of activities that precede activity 2004?



Answer : A


Question 7

What is the workweek period for this project?



Answer : D


Page:    1 / 14   
Total 120 questions