[Responsibilities and Qualifications]
The installation contractor is required to secure an advance agreement that concerns all the installation details from the:
Answer : C
[Inspection and Testing Requirements]
Gunning test panels are constructed with removable back panels:
Answer : B
[Material Requirements]
Which of the following conditions must be met for test results from trial mixes of low cement castables to be accepted for qualification?
Answer : A
[Inspection and Testing Requirements]
From each production run, the testing frequency for erosion service refractory is one sample per:
Answer : B
[Terms, Definitions, and Abbreviations]
Which of the following is the term for aggregate and/or cement that bounces away from a surface against which refractory is being projected by gunning?
Answer : C
[Material Requirements]
Each sample tested in accordance with ASTM C181 for workability index shall consist of how many specimens?
Answer : C
[Material Requirements]
When water is used for refractory installed on a carbon steel surface with a stainless steel anchorage, the chloride content of the potable water shall not exceed:
Answer : A