API-936 Refractory Personnel Exam Practice Test

Page: 1 / 14
Total 85 questions
Question 1

[Installation Procedures]

All newly installed air-setting, hydraulic, and chemically bonded linings should be allowed to cure at the proper temperature before initial heating for a minimum of:



Answer : C


Question 2

[Responsibilities and Qualifications]

The installation contractor is required to secure an advance agreement that concerns all the installation details from the:



Answer : C


Question 3

[Installation Procedures]

Refractory samples cast during the mock-up are cured for a minimum of:



Answer : D


Question 4

[Inspection and Testing Requirements]

An alternative to wire mesh baskets is a panel with enclosed sides when the:



Answer : B


Question 5

[Installation Procedures]

Which of the following is a longitudinally hinged anchoring system for curved applications?



Answer : D


Question 6

[Installation Procedures]

When installing refractory castables in hot weather conditions, which of the following is acceptable? (This may have more than one correct answer; please select all that apply.)



Answer : A, C, D


Question 7

[Installation Procedures]

For qualification testing, test panels for pneumatic gunning are inclined at a:



Answer : B


Page:    1 / 14   