APICS Certified in Production and Inventory Management Exam Practice Test

Page: 1 / 14
Total 588 questions
Question 1

The time needed to unload and load must be shorter than .



Answer : A


Question 2

If the run time per piece on operation B is shorter than that on A, the first batch must be larger enough to avoid idle time on operation A



Answer : B


Question 3

Backward scheduling is used to determine when an order must be started.



Answer : A


Question 4

When the last operation is on the routing is scheduled first and is scheduled for complete at the due date, this is called:



Answer : D


Question 5

Which file contains a list of the single-level components and quantities needed to assemble a parent?



Answer : B


Question 6

The time a job waits at a work center before being handled is called:



Answer : A


Question 7

Which file contains information on the capacity and move, wait, and queue times associated with the center?



Answer : A


Page:    1 / 14   
Total 588 questions