BCS ISEB-PM1 BCS Foundation Certificate in IS Project Management Exam Practice Test

Page: 1 / 14
Total 625 questions
Question 1

You are in a meeting with someone who just ate a slice of garlic bread. Your are distracted by his pungent breath. Which of the following communication barriers describe these distractions?



Answer : E


Question 2

A project manager has made a change to the project. What should she do NEXT?



Answer : B


Question 3

If the earned value (EV) is $1000, actual cost (AC) is $800, and planned value (PV) is $1500, what

would be the cost performance index (CPI)?



Answer : C


Question 4

What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115, and a worst case scenario of $165?



Answer : C


Question 5

What is a hierarchically organized depiction of the identified project risks arranged by risk category?



Answer : B


Question 6

Which of the following is a strategy to deal with positive risks or opportunities?



Answer : C


Question 7

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected:

Actual cost = $50,000

Plan cost = $45,000

Earned value = $40,000

What is the cost performance index?



Answer : A


Page:    1 / 14   
Total 625 questions