BCS ISEB-PM1 BCS Foundation Certificate in IS Project Management Exam Practice Test

Page: 1 / 14
Total 625 questions
Question 1

You are a project manager for Picture Shades, Inc. It manufactures window shades that have replicas of Renaissance-era paintings on the inside for hotel chains. Picture Shades is taking its product to the home market, and you're managing the new project. It will offer its products at retail stores as well as on its website. You're developing the project schedule for this under-taking and have determined the critical path. Which of the following statements is true?



Answer : A

The CPM calculates a single early and late start date and a single early and late finish date for each activity. Once these dates are known, float time is calculated for each activity to determine the critical path. The other answers contain elements of PERT calculations.


Question 2

Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?



Answer : B


Question 3

A(n) _____ is defined as a specified accomplishment in a particular instant in time which does not consume time or resources.



Answer : A


Question 4

The use of quality circles:



Answer : E


Question 5

The project manager and project sponsor are discussing the project costs and whether it is better to have their own company do part of the project or hire another company to do the work. If they asked for your opinion, you might say it would be better to do the work yourself if:



Answer : A


Question 6

Which of the following inputs is required for the WBS creation?



Answer : D


Question 7

All of the following are tools of Perform Quality Control EXCEPT:



Answer : A


Page:    1 / 14   
Total 625 questions