BCS ISEB-PM1 BCS Foundation Certificate in IS Project Management Exam Practice Test

Page: 1 / 14
Total 625 questions

Question 1

During which process would you obtain stakeholders' formal acceptance of the completed project scope?



Answer : B

Question 2

When are deliverables accepted or not accepted?



Answer : B

Question 3

Which is an input to the Scope Verification Process?



Answer : D

Question 4

Which is a tool used in monitoring and controlling project work?



Answer : B

Question 5

Information collected on the status of project activities being performed to accomplish the project work is known as what?



Answer : B

Question 6

Which tool and technique is used to sequence activities?



Answer : C

Question 7

Which is the duration of the project?



Answer : D

Page:    1 / 14   
Total 625 questions