BCS ISTQB-BCS Certified Tester Advanced Level- Test Analyst TA12 Exam Practice Test

Page: 1 / 14
Total 70 questions
Question 1

Working together with the test manager during test planning, which of the following activities is NOT expected to be performed by the test analyst?

[K2] 1 credit



Answer : C


Question 2

Tax system

A tax system needs to be updated due to new legislation. For a person with a salary of less than

20.000 and who is married, the tax needs to be re-calculated. If the person also has more than two and less than five children, an additional 10% reduction is applicable.

How many cases are required to test the ''Tax system'' specification using a decision table which is not collapsed?

[K3] 2 credits



Answer : D


Question 3

Which of the following BEST explains the use of cause-effect graphing?

[K2] 1 credit



Answer : A


Question 4

According to the ISTQB Advanced syllabus, which of the following would be the MOST effective method of communication between test team members who are distributed across several time zones?

[K2] 1 credit



Answer : A


Question 5

Which of the following criteria on test progress would enable the business to determine a likely 'go live' date?

(i) Number of tests planned versus number of tests executed

(ii) Number of high priority defects outstanding

(iii) The test team's timesheets in order to show how much effort has been devoted to testing

(iv) Number of tests passed and number failed

(v) Number of defects found in each development area

(vi) The rate at which defects are being found

[K2] 1 credit



Answer : C


Question 6

As a test analyst you are involved in the early stages of an acceptance test for a Product Data Management system. You are asked to write test designs and test cases based on use cases. An early version of the system is also already available. It is a known fact that on the implementation level many things will change (including the user-interface). The tests will be carried by end-users with much domain knowledge who have also been involved in the project defining the user requirements and reviewing documentation.

What is the BEST option regarding the level of detail and documentation required for test cases in the project?

[K4] 3 credits



Answer : D


Question 7

Which of the following statements is TRUE with respect to when the test analyst should become involved during different lifecycle models?

[K2] 1 credit



Answer : D


Page:    1 / 14   
Total 70 questions