BICSI Registered Communications Distribution Designer RCDDv14.1 Exam Practice Test

Page: 1 / 14
Total 320 questions
Question 1

A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives.

How should the program manager demonstrate the program's progress"?



Answer : A


Question 2

A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.

Which of the following deliverables captures these items?



Answer : C


Question 3

In which of the following design phases does the ICT distribution designer perform coordination with stakeholders and other disciplines (e.g.. mechanical, architectural, electrical) to ensure that the design is constructive and that any conflicts are resolved early in the process?



Answer : B


Question 4

The marketing department of a firm has tasked the organization to design a structured cabling system allowing them to support either 10G6aseT or HDBASE-T. The budget requires that only one cable type be installed and that it be MINIMUM compliant. Of the following choices, what is the choice with the MINIMUM solution/solutions for the client?



Answer : C


Question 5

A program delivers incremental benefits but is far from closure. The company completes an acquisition and defines new strategic objectives.

What should the program manager do next?



Answer : D


Question 6

The program selection committee presents several programs for approval:

Which program was selected based solely on a three-year return on investment?



Answer : C


Question 7

Which service is NOT typical of Grade 1?



Answer : B


Page:    1 / 14   
Total 320 questions