BICSI RCDDv14.1 BICSI Registered Communications Distribution Designer Exam Practice Test

Page: 1 / 14
Total 320 questions
Question 1

What is the derating factor for a 24 AWG (0.51 mm) stranded cords?



Answer : B


Question 2

Which two of the following apply during a project's close out process? (Choose two.)



Answer : A, E


Question 3

66-style connecting blocks (certain designs) can support up to what category of transmission performance?



Answer : C


Question 4

What is a simplified cone of protection for lightning strikes as it pertains to a structure (building, pole, etc.)?



Answer : C


Question 5

An ICT distribution designer working for the owner receives a submitted product that differs from the product specified in the contract documents. The original product is unavailable due to shipping or manufacturing delay. Which action should the ICT distribution designer take?



Answer : C


Question 6

Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule

What should the program manager do?



Answer : D


Question 7

A program with objectives trial impact a large segment of the population receives negative commentary from organizations representing the public interest What action should the program manager take first?



Answer : A


Page:    1 / 14   
Total 320 questions