BICSI RCDDv14.1 BICSI Registered Communications Distribution Designer Exam Practice Test

Page: 1 / 14
Total 320 questions
Question 1

A new component project is approved by the program governance board. The funding for this component project will be provided by an organization different from the organization funding the program

Would this be an acceptable funding arrangement?



Answer : B


Question 2

When designing for horizontal pathways in an environment that requires fire-stopping for penetrating a rated wall, what is the MAXIMUM till ratio for telecommunications cabling in a cable tray?



Answer : B


Question 3

In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?



Answer : B


Question 4

The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality and schedule objectives have been me, but costs and resource utilization are higher than expected The program can no longer deliver the planned return-on-investment within an acceptable level and the intended benefits have not yet been realized

After further analysis of the performance indicators the program manager should do which of the following*?



Answer : C


Question 5

An ice cream company wants to introduce a new flavor to a new market. The executive sponsor requests a sampling for the test market and the sample group provides negative feedback As this type of program had previously been conducted by the company, the program manager questions whether similar results were experienced during testing.

What should the program manager do next?



Answer : D


Question 6

Which two of the following items should be considered for inclusion in a comprehensive working outline of a SoW? (Select two options.)



Answer : A, D


Question 7

An organization requests that a junior project manager, with no previous experience or training in the industry take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.

How should the junior project manager respond to this request?



Answer : B


Page:    1 / 14   
Total 320 questions