BICSI RCDDv14 BICSI Registered Communications Distribution Designer (RCDD) Exam Practice Test

Page: 1 / 14
Total 288 questions

Question 1

Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule

What should the program manager do?



Answer : D

Question 2

A program with objectives trial impact a large segment of the population receives negative commentary from organizations representing the public interest What action should the program manager take first?



Answer : A

Question 3

A program manager assigns project managers lo five component projects and continues to develop the program team. Which of the following represents the program manager's strategy?



Answer : B

Question 4

When should a program manager approve the closure of a component project?



Answer : A

Question 5

A program manager is working with the sponsor, stakeholders, and steering committee to formulate a program's benefits sustainment and transition plan What should the program manager do to create this plan?



Answer : D

Question 6

A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.

Which of the following deliverables captures these items?



Answer : C

Question 7

A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting. What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program'?



Answer : C

Page:    1 / 14   
Total 288 questions