CIPS Procurement and Supply in Practice L4M8 Exam Questions

Page: 1 / 14
Total 200 questions
Question 1

SIMULATION

KPI should be written to match which area of an organization?



Answer : A

Key performance indicator (KPI) is another method of monitoring how a supplier is delivering on a contract.

When creating KPIs to manage suppliers and their contracts the areas monitored should be related to the organization's overall strategy that is where organization's success will be measured.


Question 2

SIMULATION

What is contract performance review and continuous improvement?



Answer : A

Contract performance review and continuous improvement is the stage 11 of the CIPS procurement and supply cycle.

In order to effectively manage supplier performance and contractual obligations, the suppliers per-formance against key performance indicators (KPI) should be reviewed regularly. This KPI should have been agreed doing the post contract award negotiation. In addition to review KPIs suppliers and the procurement team should work towards continuous improvement. This is a continuous ef-fort to improve product or services within an organization. This may involve improving quality, reducing waste in the supply chain and focusing on innovation. It is an ongoing process that works toward perfection.


Question 3

SIMULATION

What are the four stages of decommissioning?



Answer : A

When a fixed asset reaches the end of its life, it requires decommissioning before reconditioning or disposal.

Decommissioning is to observe all the safety measures and technical procedures and stop active machinery or an asset from operation (example gas plan, generator, transformer etc.

Decommissioning process include the following aspect

1) Preparation: Plan the process

2) Dismantle: Take the asset apart and remove hazardous waste

3) Processing: make safe any hazardous waste

4) Disposal: Ensure paper work is received to confirm removal and disposal


Question 4

SIMULATION

What are Carter's 10Cs?



Answer : A

Carter's 10cs is a detailed mechanism that procurement professional uses to evaluate potential supplier. What the procurement professional should consider in supplier are the following 10 things.

1) Competency 2) capacity 3) Cost 4) Cash 5) Clean 6) Consistency 7) Control 8) Cul-ture 9) Commitment 10) Communication.


Question 5

SIMULATION

Describe what should be considered when creating damages terms in a contract.



Answer : A

Damages are 'sum of money that the supplier pays if it fails to carry out its contractual obligation.

When creating terms for damages in the contract, it should be considered that Damages are categorized into two types (liquidated and un-liquidated). And which or if both are applicable to the contract in hand.

Liquidate Damages are fixed amount of money agreed between the parties that is payable if a contract is breached. For example, knowing that supplier not being able to install a device properly in a power transformer may destroy the device and going ahead to include a fee in the contract if the device was destroyed.

Un-liquidated damages are unfixed amount of money. It is used when the amount of money that will compensate the injured party cannot be known in advance. A court decides the amount when the damages occur. For example, knowing that supplier not being able to install a device properly in a power transformer may destroy the device, other appliances and equipment unknown, cause the buyer delay in the process and reputational damage as in customer dissatisfaction. Yet, unquantifiable as both parties are unable to fix a fee in advance on the damages and leaving it to the court to decide the damage if it may occur.

*

Refer to the question column for response


Question 6

SIMULATION

What are the two options for the disposal of an asset if resale is not possible?



Answer : A

Disposal of an asset is the final stage in the decommissioning process of a fixed asset.

When a fixed asset reaches the end of its useful or cost effective life time within an organization, the decision is made as to whether it should be removed from the premises or disposed off.

If the asset is truly at the end of its life, no longer fit for purpose, not cost effective to repair and is not able to be exchanged, then disposal is the only option; there are two options for disposal;

1) Take the asset to land fill site

2) Taking the asset to a recycling plant.

*

Refer to the question column for response


Question 7

SIMULATION

What are the definition of a new buy and a modified re-buy?



Answer : A

A new buy is the purchase of goods and services by an organization or an individual for its first time. For example a transport organization for the very first time contracting the purchase of a Lorry out to an external supplier. In situations like this, it is advisable to start the procurement cycle from the very first stage. Which is understanding the need and developing high level specification.

Modified re-buy is the purchase of goods or services that an organization has bought before there was a need but with changes to the specification or supplier or quantity or quality. In carrying out modified re-buy, procurement professional should start from the very first stage of the procurement cycle to justify the added need and follow through. Not in all cases that buyer would have to start from understanding the need. In a situation where the changes required is a change of supplier, the organization will start from its preferred suppliers list and contract the next ranking supplier as the case may be.

*

Refer to the question column for response


Page:    1 / 14   
Total 200 questions