CIPS Project and Change Management L5M8 Exam Questions

Page: 1 / 14
Total 88 questions
Question 1

What is meant by ''resource levelling''?



Answer : D

Resource levelling adjusts resource allocations to balance demand vs. capacity constraints over time (adding when workload peaks; releasing when it ebbs) to reduce bottlenecks.


Question 2

Derek is a Project Manager at Dandelion Ltd and is beginning the project initiation phase of a new project looking into the creation of a new product line. He is creating a business case for senior leadership. Should Derek include within this risks and concerns he has about the potential failure of the project?



Answer : A

A realistic business case should clearly outline risks and concerns with contingencies, so leaders can judge whether benefits outweigh risks and avoid surprise later.


Question 3

Screwdriver Ltd runs a Lean manufacturing process and has recently sequenced its supply chain. It discovered that there is an average two-day delay between the completion of task 1 and task 2. What type of cost is this?



Answer : A

An interchange cost arises when there is inefficiency or delay between process stages in the value stream. In Lean thinking, ideal flow minimises these gaps to improve cycle time and efficiency.


Question 4

During the convergence phase of a market lifecycle, which of the following are true? Select TWO



Answer : C, D

In the convergence phase, products/services become standardised, competition intensifies, and firms seek cost efficiency. Mergers and acquisitions increase as companies consolidate to sustain market position.


Question 5

Which of the following is an example of an exogenous disruption that stimulates the requirement for change within an organisation?



Answer : C

An exogenous driver of change originates outside the organisation. A tax rate increase is an external policy change; the other options are internal.


Question 6

Cleo is a Project Manager and is drafting a set of objectives for her project. She has decided that the project must have completed stages 1 and 2 before the end of the financial year. This is an example of what type of objective?



Answer : D

In SMART objectives, ''time-bound'' refers to setting a deadline or timeframe. Cleo's inclusion of the end of the financial year defines clear timing.


Question 7

The analysis of roles, relationships and interdependencies within the supply chain network requires evaluation only at the start of a project. Is this correct?



Answer : C

The CIPS guide highlights that supply network roles and relationships evolve during project execution. Therefore, they must be reviewed regularly, not just initially, to maintain alignment and manage interdependencies effectively.


Page:    1 / 14   
Total 88 questions