CIPS Strategic Programme Leadership L6M5 Exam Questions

Page: 1 / 14
Total 83 questions
Question 1

Josh is the son of the CEO of a law firm and has recently been hired as a trainee attorney, following his graduation from University. He has been with the company for three months and middle management often invite him to meetings that other trainee attorneys are not invited to. What type of power does he have that would explain this?



Answer : A

Josh's access is due to his family connection, which is an example of positional power.


Question 2

A person who disrupts progress and hinders culture change holds which type of power?

Answer Options:



Answer : D

Negative Power (p.199) refers to individuals obstructing progress in an organization.

Dismissive (A) means ignoring opinions.

Contrary (B) and Pessimistic (C) do not refer to organizational influence. [P.199]


Question 3

Robyn has created a contract for a construction project and has used "The Red Book."

Q: Which professional organization is responsible for creating this contract?

Answer Options:



Answer : D

The Red Book is part of the FIDIC 'Rainbow Suite' of contracts (p.40). FIDIC contracts are categorized by color, each serving a specific purpose in construction and engineering projects. [P.40]


Question 4

Manchester City Council is planning to construct a new hospital using an EPC style of contract. Which two of the following are the greatest risks to the Council?



Answer : A, C

The main risks are ensuring that the specification is correct and that the requirements are accurately communicated to the contractor.


Question 5

In which scenario would a Cost Reimbursable contract be most suitable?

Answer Options:



Answer : A

Cost Reimbursable contracts are widely used in research projects where the exact scope is uncertain (p.69). These contracts allow for flexibility in cost adjustments based on project progress. Option B describes a contract using cost-plus pricing, and Options C and D do not fit this contract model. [P.69]


Question 6

At what stage in a program's lifecycle is an Investment Appraisal conducted?

Answer Options:



Answer : A

Investment Appraisal is performed before a program is approved (p.69). It evaluates whether the project is financially viable and likely to provide a return on investment. Option B relates to procurement, and Options C and D are post-implementation assessments. [P.69]


Question 7

Golden Rainbow Ltd has invested 4m in a new research project started three years ago. The CFO calculates that the average rate of return on the project is --6%. Is this possible?



Answer : A

A negative rate of return indicates that the project is generating a loss of 6% per annum.


Page:    1 / 14   
Total 83 questions