CompTIA PK0-004 CompTIA Project+ Exam Practice Test

Page: 1 / 14
Total 574 questions

Question 1

Which of the following is the project phase when quality assurance occurs?



Answer : C

Question 2

The vendor management team has requested all project managers to provide proof to back up complaints on vendor resolution delays.

Which of the following will provide this information?



Answer : D

Question 3

Joe, a stakeholder, threatens to withdraw from a project that is not going according to his wishes. The president talks to the project manager regarding options for a response to the stakeholder, and they decide the

project will move forward as originally planned.

Which of the following risk strategies was used?



Answer : A

Question 4

A project manager has gathered time estimates for a new project's activities and is now ready to begin developing the schedule.

Which of the following would the project manager most likely do NEXT?



Answer : A

Question 5

On larger projects, a vendor may occasionally proceed upon receipt of the:



Answer : D

Question 6

Which of the following project management tools provides an authoritative source of the project performance guidelines?



Answer : A

Question 7

Project cost control deals with:



Answer : B

Page:    1 / 14   
Total 574 questions