CompTIA Project+ Certification PK0-005 Exam Practice Test

Page: 1 / 14
Total 386 questions
Question 1

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).



Answer : E, F


Question 2

Which of the following software programs would be BEST to use lo store information related to business transactions?



Answer : B


Question 3

A project is not progressing as planned following the departure of the project manager. Which of the following would be the best tool to use to document this information?



Answer : A


Question 4

The goal of a project is to fulfill specific technical features requested by customers. Which of the following actions should the product owner take?



Answer : A


Question 5

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?



Answer : A


Question 6

A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?



Answer : A


Question 7

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?



Answer : C


Page:    1 / 14   
Total 386 questions