CompTIA PK0-004 CompTIA Project+ Exam Practice Test

Page: 1 / 14
Total 796 questions
Question 1

A project audit resulted in a report that outlined numerous defects. Which of the following is being performed?



Answer : A


Question 2

Project team members are getting frustrated, questioning their goals, and taking it out on their project manager. In which of the following stages is the team?



Answer : B


Question 3

A quality manager is detailing performance results, which show an exponential trend. Which of the following tools should be used to demonstrate this visually?



Answer : C


Question 4

Which of the following is an attribute of a potential project?



Answer : A


Question 5

Prior to engaging a vendor on an RFI, which of the following documents protects the company's interests?



Answer : A


Question 6

A project management team is discussing a potential risk event that would be devastating to the organization and prohibitively expensive to mitigate or insure against if it occurred. Which of the following is the BEST risk strategy to adopt?



Answer : D


Question 7

A project team is assessing individual project risks by evaluating the probability tor each one to occur, as well as the potential impact to project objectives using low, medium, and high values. The process the project team is using is known as:



Answer : B


Page:    1 / 14   
Total 796 questions