CompTIA PK0-005 CompTIA Project+ Certification Exam Practice Test

Page: 1 / 14
Total 362 questions
Question 1

As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world Which of the following should the project manager consider doing as part of the project planning?



Answer : B


Question 2

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).



Answer : C, E


Question 3

A system is scheduled to go live, and the client signed an SL



Answer : A, A


Question 4

Which of the following software programs would be best to use to store information related to business transactions?



Answer : C


Question 5

A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?



Answer : B


Question 6

A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?



Answer : D


Question 7

Which of the following tools is best to use for storing lessons learned?



Answer : B


Page:    1 / 14   
Total 362 questions