CompTIA Project+ Certification (2026) PK0-005 Practice Questions

Page: 1 / 14
Total 447 questions
Question 1

As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Select two).



Answer : D, E

The project manager should approve the deliverables and monitor the performance of the outsourced structured cabling activities. These are the responsibilities of the project manager when dealing with external vendors or contractors, as they ensure that the quality standards, scope, schedule, and budget are met according to the contract terms and the project plan. The project manager should also communicate regularly with the vendor and provide feedback and guidance as needed. The other options are not correct because:

Purchasing the materials is not the responsibility of the project manager, but the vendor who is performing the structured cabling activities. The project manager should only verify that the materials are suitable and available for the project.

Assigning the resources is not the responsibility of the project manager, but the vendor who is performing the structured cabling activities. The project manager should only ensure that the vendor has the adequate and qualified resources to complete the work.

Accepting delays in the work is not a good practice for the project manager, as it can negatively affect the project schedule, scope, and quality. The project manager should proactively identify and manage the risks and issues that may cause delays, and implement contingency plans or corrective actions if necessary.

Negotiating with the vendors is not a task that the project manager should do during the execution of the structured cabling activities, as it should have been done during the planning and procurement phases of the project. The project manager should only adhere to the contract terms and conditions that have been agreed upon with the vendor, and only renegotiate if there are significant changes or disputes that require it.References=CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 8: Planning Projects, Part 4 (Procurement and Communication), pages 243-260;CompTIA Project+ Certification Exam Objectives, Domain 2: Project Planning, Objective 2.5: Given a scenario, plan procurement for a project; Domain 3: Project Execution, Objective 3.2: Given a scenario, execute and monitor project tasks using traditional methodologies.


Question 2

A project manager would like to add external engineers to the current team. Engineers will participate in specific tasks only during the testing phase. Which of the following contracts would the project manager most likely use in this situation?



Answer : A

A time and materials (T&M) contract is the best fit when you need temporary, specialized resources for a limited period (here, only during the testing phase) and the exact effort/hours are not fully predictable. With T&M, the buyer pays for the actual labor time (often at an agreed hourly/daily rate) and any approved materials/expenses. This aligns to CompTIA Project+ procurement objectives around selecting appropriate contract considerations and types, where time and material is a standard option used when work is phase-specific or scope is not fully defined to a fixed deliverable.

By contrast, fixed-price is most appropriate when the scope and deliverables are clearly defined upfront (less suitable for staff augmentation). Cost-plus reimburses allowable costs plus a fee and is typically used for broader, less-defined deliverables---often creating higher buyer cost risk than T&M for a small, contained staffing need. A warranty is not a primary contract type for acquiring temporary engineers; it's usually a contract provision related to quality/defects after delivery.


Question 3

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?



Answer : A

Scope creep is most likely happening when a key stakeholder recommends to a senior developer that a new feature be added that is not part of the current requirement documentation. Scope creep is a term that refers to the uncontrolled expansion or change of a project's scope beyond its original boundaries or objectives. Scope creep can happen due to various reasons, such as changing customer demands, unclear or incomplete requirements, poor communication, lack of change control, or stakeholder interference.Scope creep can have negative impacts on a project, such as delays, cost overruns, quality issues, or reduced customer satisfaction12


Question 4

A project sponsor tells the project manager that new regulatory environment changes are coming in the next month. Which of the following should the project manager do next?



Answer : D

Because the regulatory change is anticipated (''coming in the next month'') and has not yet impacted the project, it should be treated as a risk (a potential future event) rather than an issue (a current problem). The correct next step is to add the risk to the risk register so it can be assessed for probability/impact, assigned an owner, and have response actions planned (avoid/mitigate/transfer/accept and contingency plans). This aligns with CompTIA Project+ risk management expectations: using the risk register to capture and manage upcoming threats that could affect scope, schedule, cost, or compliance obligations.

The other options don't fit ''next.'' An issue log is for something that is already occurring and needs resolution now. A CCB is used when a specific change request is ready to be evaluated/approved, but at this point the PM needs to first understand the regulatory impact and options (which begins with risk capture and analysis). A work-around is a temporary fix for an active problem, which does not apply to an upcoming regulatory change. The PM should document the risk, analyze impact, and then---if needed---raise change requests once requirements and compliance impacts are clear.


Question 5

A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?



Answer : A

Assigning a scribe allows the project manager to focus on hosting and facilitating the meeting effectively without being distracted by note-taking. This approach is consistent with best practices in meeting management and aligns with CompTIA Project+ guidelines, which emphasize the importance of efficient meeting roles and responsibilities.


Question 6

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?



Answer : A

The project manager should put in place a time and materials contract before work begins for a third party that needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. A time and materials contract is a type of contract where the buyer pays the seller based on the actual time spent and materials used during the project. A time and materials contract is suitable for projects that have uncertain or variable scope, duration, or cost. A time and materials contract can provide flexibility and adaptability for both parties and allow them to adjust to changing requirements or circumstances.


Question 7

Which of the following should be considered first when determining the privacy management for project data?



Answer : B

Before starting a new project that involves personal data, the project manager should first understand the relevant privacy regulations that apply to the data subjects, the data controllers, and the data processors. These regulations may vary depending on the location, industry, and nature of the data. For example, GDPR applies to any project that processes the personal data of individuals in the European Union, regardless of where the project is based or executed. Understanding the applicable privacy regulations will help the project manager to identify the legal obligations, risks, and compliance requirements for the project data. References = CompTIA Project+ Study Guide, Chapter 3: Project Planning, Section 3.4: Data Privacy and Security, p. 121-122; A Project Management Approach to Data Protection Compliance; 10 Data Protection Considerations Before Starting a New Project; Project Teams Must Manage Risk and New Requirements to Ensure Data Privacy


Page:    1 / 14   
Total 447 questions