A team selects a Product Backlog Item (PBI) for the Sprint Backlog.
What must a team do to finish the Product Backlog Item it selects?
Answer : B
During a Sprint Planning session, the team argues about the work estimates for a particular story.
The Product Owner estimates five days.
The Lead Architect estimates two days.
The Scrum Master estimates eight days.
The team member working on it estimates seven days.
What value (in days) should be used for planning?
Answer : C
What is meant by the velocity of the team?
Answer : C
What is a Scrum-of-Scrums?
Answer : C
What is an information radiator?
Answer : A
In a Scrum project, when would a requirement get added to the Product backlog?
Answer : C
Under what circumstances would a team use Affinity Estimation Technique instead of Planning Poker?
Answer : B