Exin Agile Scrum Foundation ASF Exam Questions

Page: 1 / 14
Total 59 questions
Question 1

A Scrum team failed to meet the Sprint objectives. One of the key members of the team fell ill and was away for two days right at the beginning of the four week Sprint.

What is the most likely reason that the team did not meet the Sprint objectives?



Answer : C


Question 2

A team is trying to convince a customer about the value of adopting Scrum. The customer likes some of the features of the methodology like the bi-weekly demonstration, but the customer remains largely unconvinced of the value of Scrum and refuses to change the way of working,

What should the team do?



Answer : C


Question 3

During a Sprint Planning session, the team argues about the work estimates for a particular story.

The Product Owner estimates five days.

The Lead Architect estimates two days.

The Scrum Master estimates eight days.

The team member working on it estimates seven days.

What value (in days) should be used for planning?



Answer : C


Question 4

In a Scrum project, when would a requirement get added to the Product backlog?



Answer : C


Question 5

Which of the following statements best expresses the role that the daily stand-up meeting plays in the monitoring of a Scrum project?



Answer : B


Question 6

Why are estimates expressed in terms of story points difficult to explain outside of the team?



Answer : A


Question 7

What is a Sprint?



Answer : C


Page:    1 / 14   
Total 59 questions