Exin Agile Scrum Foundation Exam Practice Test

Page: 1 / 14
Total 59 questions
Question 1

During a Sprint Planning session, the team argues about the work estimates for a particular story.

The Product Owner estimates five days.

The Lead Architect estimates two days.

The Scrum Master estimates eight days.

The team member working on it estimates seven days.

What value (in days) should be used for planning?



Answer : C


Question 2

What is a characteristic of a well-designed Agile work space?



Answer : B


Question 3

What is time-boxing?



Answer : B


Question 4

What is the usual length of the time box for the complete Sprint Planning meeting?



Answer : A


Question 5

A Manager requests to attend the daily stand-up meeting so that he can be more responsive to the team by being aware of the team's progress and issues.

As the Scrum Master, what should you do?



Answer : A


Question 6

When is a Sprint complete?



Answer : C


Question 7

The Product Owner is going on a three-week vacation. The team should be closing the current Sprint and starting a new Sprint at the end of the first week of the Product Owner's vacation.

What is the best way to continue the Scrum rituals in this situation?



Answer : C


Page:    1 / 14   
Total 59 questions