Exin ASM Agile Scrum Master Exam Practice Test

Page: 1 / 14
Total 230 questions
Question 1

Each Scrum role has specific responsibilities in managing a Scrum project. Below, choose the role that is

correctly matched to its responsibility.



Answer : B

:

Although the Stakeholder(s) and the Product Owner have the final say on Prioritized Product Backlog Items

and whether to accept or reject any Change Requests presented during Demonstrate and Validate Sprint, it is

the Scrum Master's responsibility to ensure that the requirements and Acceptance Criteria are not altered

during the Sprint Review Meeting for the User Stories completed in the current Sprint. This prevents the

rejection of completed User Stories based on the fact that they do not meet newly changed requirements. If

any requirements need to be changed, any corresponding PBI needs to be revised to accommodate the

modified requirements in a future Sprint.


Question 2

Kevin is a Product Owner for a retail organization. The Product Backlog for his immense marketing tool project has 200 Product Backlog Items.

Into what should he group the smaller Stories together?



Answer : B


Question 3

After the creation of the Release Plan, the Product Owner says:

Over the next four months with eights two-week Sprints we will complete exactly 240 Story Points of work.

The Scrum Master argues that the end date of the release can be positively or negatively impacted by three factors. Completed work is the first factor.

What are the other two factors?



Answer : B


Question 4

Program Stakeholders, the Program Product Owner, Program Scrum Master, and Chief Product Owner have

gathered together to create the Project Vision. They are trying to determine and document the difference

between current business capabilities and the final desired set of capabilities. Which one of the following

should they use to arrive at a conclusive decision?



Answer : C


Question 5

Which of the following best describes why Epics are decomposed into smaller User Stories during a Sprint?



Answer : A


Question 6

Which of the following meetings is not usually Time-boxed?



Answer : B


Question 7

A Scrum Team wants to conduct a meeting in which they plan to deliberate on ways to improve team

collaboration and effectiveness in future. This can be identified as which type of meeting?



Answer : A


Page:    1 / 14   
Total 230 questions