Exin EPI Certified Data Centre Specialist CDCS Exam Questions

Page: 1 / 14
Total 120 questions
Question 1

A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center.

Are new floor loading calculations required?



Answer : D

For heavy equipment, such as a network storage device weighing approximately 600 kg/1,300 lbs, new floor loading calculations are indeed required, particularly since the rack is non-standard. A structural engineer, approved by the building owner, should conduct these calculations to ensure the floor can safely support the new load without risking structural integrity.

Detailed Explanation:

Data centers are designed with specific floor load ratings, which are determined during the design phase based on anticipated equipment. When adding or replacing equipment that is significantly heavy or non-standard, reassessing the floor's capacity is essential to avoid overloading. A structural engineer has the expertise to verify if the existing floor can accommodate the weight and, if not, can recommend reinforcement measures.

This step ensures compliance with safety standards and helps prevent damage to the infrastructure, which could lead to costly repairs or even catastrophic failure in extreme cases.

EPI Data Center Specialist Reference:

EPI Data Center Specialist training advises that any changes in the data center load, particularly involving non-standard and heavy equipment, warrant a structural assessment. Ensuring compliance with floor load capacity is a critical safety and operational concern, as underscoring data center infrastructure reliability and safety is a priority in EPI's best practices.


Question 2

The building requires sprinklers and is equipped with a wet-pipe system. What action should you recommend for the computer room?



Answer : C

NFPA 75 (IT equipment rooms) recommends pre-action sprinklers for data processing spaces to minimize accidental water discharge risk; wet-pipe is generally discouraged directly over IT hardware.


===========

Question 3

Where should raised-floor installation start?



Answer : C

Best practice is to begin raised-floor installation at the center of the room, working outward. This minimizes alignment errors and ensures the tile grid is centered, which is critical for aisle containment and rack alignment.

Starting at the perimeter (A, B, D) causes cutting of tiles along both sides, misalignment with rack rows, and possible airflow inefficiencies. By starting at the center, tiles can be cut symmetrically around the edges, providing better aesthetics, balanced airflow, and structural stability.

Industry guidelines such as CISCA recommend this approach for raised floors in mission-critical spaces.


Question 4

A computer room with a raised floor has been designed with racks in a hot/cold aisle setup.

What should you recommend for the placement of down-flow air conditioners?



Answer : A

In a hot/cold aisle configuration, placing down-flow air conditioners perpendicular to the cold aisle ensures that cool air is directed efficiently into the cold aisles where server intakes are located. This layout allows for optimal cooling performance by aligning the airflow directly with the equipment intakes, minimizing hot spots and enhancing cooling efficiency.

Detailed Explanation:

With a raised floor design, cold air from the air conditioners is supplied into the cold aisle, where server intakes are located. Positioning the air conditioning units perpendicular to the cold aisles ensures that cool air is delivered directly into these aisles, preventing air mixing and optimizing cooling. This setup takes full advantage of the airflow management strategy inherent to the hot/cold aisle configuration.

EPI Data Center Specialist Reference:

EPI guidelines on cooling emphasize that down-flow air conditioners should be positioned to maximize the effectiveness of cold aisle delivery, which improves cooling efficiency and helps maintain consistent temperatures across server racks.


Question 5

A customer requires THDi from the UPS not to exceed 3% and wants high efficiency. The UPS has a 6-pulse SCR/thyristor rectifier and is loaded ~80%. Many ICT changes are expected in the next 3 years. What should you recommend?



Answer : C

A 6-pulse thyristor rectifier typically produces 25--35% THDi at nominal load. To reach 3% THDi, an active harmonic filter (or a 12/18-pulse or IGBT rectifier UPS) is required. Passive filters are load-specific and less effective over a wide operating range---undesirable with frequent changes.


===========

Question 6

Where should perforated tiles be installed?



Answer : C

Perforated tiles should be located in front of equipment racks, aligned with cold aisles, to deliver supply air directly to server intakes. Best practice is one perforated tile per rack, adjusted based on airflow requirements and rack load.

Placing tiles at the back (A) disrupts airflow.

Spacing every 5th rack (B) provides insufficient cooling.

Placing near AC (D) causes uneven distribution and pressure loss.

Thus, option C is correct.


Question 7

A sprinkler system employs automatic sprinklers attached to a piping system containing water and connected to a water supply so that water discharges immediately when a head opens. What is this called?



Answer : D

In a wet pipe system, the piping is always filled with water under pressure. When a sprinkler head is triggered by heat, water is discharged immediately. This is the most common sprinkler system for general buildings.

Dry pipe: Pipes contain air or nitrogen; water enters only after valve activation.

Deluge: Pipes are empty, and all heads open simultaneously, releasing water everywhere.

Pre-action: Pipes are dry until detection and valve activation; reduces accidental discharge risk, recommended for IT rooms.

Since the definition describes immediate discharge from water-filled pipes, this is a wet pipe system.


Page:    1 / 14   
Total 120 questions