Exin CDCS EXIN EPI Certified Data Centre Specialist Exam Practice Test

Page: 1 / 14
Total 60 questions
Question 1

When installing a raised floor, can we use a spirit level bar to level the floor?



Answer : B

A spirit level bar should not be used for leveling a raised floor, as measurement errors are likely to propagate from one pedestal to the next. Spirit levels can introduce cumulative errors, leading to uneven floors, particularly in large installations where precise leveling is critical.

Detailed Explanation:

Using a laser level or a precision leveling device is recommended to ensure accuracy across all floor tiles. Spirit levels, while adequate for short spans, can transfer small inaccuracies from one pedestal to another, which can cause alignment issues and floor instability over time.

EPI Data Center Specialist References:

EPI data center guidelines discourage the use of spirit levels for raised floors. Instead, they advocate for precision tools like laser levels that ensure consistency and accuracy in large-scale installations, aligning with best practices for raised floor construction.


Question 2

What is a potential disadvantage of using water mist as a fire extinguishing system?



Answer : B

A potential disadvantage of using a water mist fire suppression system is that it can rapidly increase the humidity within the data center, which may pose risks to sensitive electronic equipment. Excessive humidity can lead to condensation, which could damage electronics and lead to short circuits or corrosion over time.

Detailed Explanation:

Water mist systems use fine droplets to suppress fires by cooling and displacing heat. However, the moisture generated may raise the humidity level to the point where it exceeds safe operational limits for IT equipment. Therefore, while water mist systems are effective in fire suppression, they may not be ideal in environments where high humidity could damage sensitive equipment.

EPI Data Center Specialist References:

EPI guidelines advise considering the impact of humidity from fire suppression systems, particularly in environments housing electronic equipment. It's essential to weigh the benefits of fire suppression against potential risks to operational equipment when choosing suppression methods.


Question 3

A computer room with a raised floor has been designed with racks in a hot/cold aisle setup.

What should you recommend for the placement of down-flow air conditioners?



Answer : A

In a hot/cold aisle configuration, placing down-flow air conditioners perpendicular to the cold aisle ensures that cool air is directed efficiently into the cold aisles where server intakes are located. This layout allows for optimal cooling performance by aligning the airflow directly with the equipment intakes, minimizing hot spots and enhancing cooling efficiency.

Detailed Explanation:

With a raised floor design, cold air from the air conditioners is supplied into the cold aisle, where server intakes are located. Positioning the air conditioning units perpendicular to the cold aisles ensures that cool air is delivered directly into these aisles, preventing air mixing and optimizing cooling. This setup takes full advantage of the airflow management strategy inherent to the hot/cold aisle configuration.

EPI Data Center Specialist References:

EPI guidelines on cooling emphasize that down-flow air conditioners should be positioned to maximize the effectiveness of cold aisle delivery, which improves cooling efficiency and helps maintain consistent temperatures across server racks.


Question 4

The pipes of a VESDA smoke detection system are installed at the air intake of the air conditioner inside the computer room.

Is this a good practice from an early smoke detection point of view?



Answer : D

For optimal early smoke detection in a data center, it is crucial that the Very Early Smoke Detection Apparatus (VESDA) system be installed at locations where smoke will be detected as soon as it appears. Positioning the VESDA pipes at the air intake of the air conditioner inside the computer room is not ideal. This placement could result in a delayed detection response and the potential for bypass airflow to occur, which would impede the system's ability to detect smoke effectively.

Detailed Explanation:

When VESDA pipes are installed at the air intake, the detection system relies on the smoke to be drawn into the air conditioning unit before detection can occur. This setup increases the reaction time as the smoke has to travel through the intake and get processed by the air conditioner. Furthermore, bypass airflow---a phenomenon where not all the air containing smoke particles passes through the VESDA pipes---could also delay or even prevent the system from detecting smoke early.

Ideally, VESDA pipes should be positioned where smoke is likely to accumulate first, such as near the ceiling or in the return airflow path to detect smoke at the earliest possible stage. This ensures that the detection system can quickly trigger alarms, providing more time to address potential fire hazards.

EPI Data Center Specialist References:

EPI Data Center Specialist training highlights that smoke detection should prioritize early response capabilities to maximize safety. The preferred installation for VESDA pipes is generally at points where smoke would naturally accumulate, rather than relying on air conditioning intakes where airflow can vary and delay detection. In their course materials, EPI emphasizes minimizing reaction time and reducing the impact of airflow dynamics on smoke detection efficiency.


Question 5

A data center has its own power supply from the public utility and receives chilled water supply from the building owner.

What needs to be taken into consideration when calculating the PUE?



Answer : C

When calculating Power Usage Effectiveness (PUE) in a data center that uses chilled water from an external source, like from a building owner, a weight factor for district chilled water must be applied. This is because PUE calculations aim to measure the energy efficiency of the data center's own operations, and external utilities like district chilled water aren't directly powered by the data center. A weight factor of 0.4 is typically used to account for the energy consumed to produce and deliver the chilled water, reflecting the indirect impact on the data center's total energy consumption.

Detailed Explanation:

PUE is calculated as the ratio of the total facility energy to the IT equipment energy. If the cooling is provided by an external chilled water source, it's necessary to adjust the calculations to accurately reflect the energy impact. By incorporating the 0.4 weight factor, data centers can calculate a more accurate PUE, aligning with standard methods and industry best practices.

EPI Data Center Specialist References:

EPI training on PUE highlights the importance of adjusting for external energy sources, such as district cooling, in the calculations. This ensures that PUE values remain accurate and comparable across different data centers, even when external utilities are used.


Question 6

Is it allowed to make design changes during the implementation phase?



Answer : D

Design changes during the implementation phase are generally allowed only when there is a strong business and/or technical justification. Changes at this stage can lead to delays, increased costs, or compromise design integrity. Thus, a rigorous assessment is required to ensure any modifications are essential and provide clear benefits or address critical issues.

Detailed Explanation:

Changes post-design freeze should be minimized to avoid scope creep and additional costs. However, if a technical issue arises that would affect operational goals, or a business need warrants modification, justified changes are permissible, following an impact assessment and approval process.

EPI Data Center Specialist References:

EPI project management guidelines recommend a controlled change management process during implementation, allowing changes only when they align with critical objectives or address unforeseen issues that affect the project's success.


Question 7

The humidity in the computer room has changed from about 50% down to 35% Relative Humidity (RH).

What influence does this have on Electrostatic Discharge (ESD)?



Answer : C

As relative humidity decreases, Electrostatic Discharge (ESD) risks increase. Lower humidity levels reduce the amount of moisture in the air, which normally helps dissipate static charges. When the humidity drops from 50% to 35%, the likelihood of static electricity accumulating on surfaces rises, leading to a higher potential for ESD incidents that could damage sensitive IT equipment.

Detailed Explanation:

ESD events are more common in dry environments because there is less atmospheric moisture to neutralize electrical charges. Maintaining relative humidity above 40% helps minimize the risk of ESD, which is why data centers often control humidity levels tightly to protect equipment from static discharge that could cause hardware failures or data loss.

EPI Data Center Specialist References:

EPI data center best practices stress the importance of maintaining stable humidity levels to prevent ESD, particularly in computer rooms. Recommended humidity ranges are typically above 40% to prevent conditions that would foster static buildup.


Page:    1 / 14   
Total 60 questions