The Plan-Do-Check-Act (PDCA) methodology can be applied to all ISO/IEC 20000 processes. What does the Act phase of this methodology cover?
Answer : D
A . Incorrect. This action is taken during the Plan phase of the methodology.
B . Incorrect. This action is taken during the Do phase of the methodology.
C . Incorrect. These are the actions taken during the Check phase.
D . Correct. This action is taken during the Act phase of the methodology.
Which of the aspects listed below is included in ISO/IEC 20000?
Answer : A
The appointed member of management is only responsible for the co-ordination and management of all services. Can this person perform internal audits for the delivery processes?
Answer : C
Where are agreements regarding Service Delivery and its relationship to Security Management recorded?
Answer : D
Which of the following statements is true?
Answer : D
What is according to ISO/IEC 20000 a required part of the planning for new or changed services?
Answer : B
Personnel should be competent on the basis of appropriate education and experience. Which of the following is a best practice relating to competence?
Answer : A
A . Correct. This is a best practice according to the standard.
B . Incorrect. This is relevant to availability of resources, however not a best practice for competency.
C . Incorrect. A bachelors degree is not a requirement, relevant training for the role is.
D . Incorrect. This is a specific training for Security, but not a best practice for competency in general.