GAQM Associate in Project Management APM-001 Exam Questions

Page: 1 / 14
Total 704 questions
Question 1

A project manager builds consensus and overcomes obstacles by employing which

communication technique?



Answer : B


Question 2

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?



Answer : C


Question 3

What are the identified risks for doing excessive decomposition in a WBS?



Answer : D


Question 4

Which of the following is an input to the Perform Qualitative Risk Analysis process?



Answer : A


Question 5

What risk technique is used to quantify the probability and impact of risks on project objectives?



Answer : D


Question 6

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?



Answer : D


Question 7

Whose approval may be required for change requests after change control board (CCB) approval?



Answer : C


Page:    1 / 14   
Total 704 questions