GAQM Associate in Project Management APM-001 APM Exam Practice Test

Page: 1 / 14
Total 704 questions
Question 1

Which tool or technique is an examination of industry and specific vendor capabilities?



Answer : B


Question 2

When the business objectives of an organization change, project goals need to be:



Answer : A


Question 3

Which project risk listed in the table below is most likely to occur?



Answer : B


Question 4

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?



Answer : B


Question 5

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?



Answer : A


Question 6

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?



Answer : A


Question 7

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?



Answer : D


Page:    1 / 14   
Total 704 questions