GAQM APM-001 Associate in Project Management APM Exam Practice Test

Page: 1 / 14
Total 704 questions
Question 1

Which of the following can be used as an input for Define Scope?



Answer : B


Question 2

After Define Activities and Sequence Activities, the next process is:



Answer : A


Question 3

The correct equation for schedule variance (SV) is earned value:



Answer : A


Question 4

Which of the following is an output of Define Scope?



Answer : A


Question 5

Inputs to the Plan Risk Management process include the:



Answer : A


Question 6

Plan-do-check-act is also known as:



Answer : D


Question 7

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:



Answer : A


Page:    1 / 14   
Total 704 questions