GAQM CTIL-001 Certified Software Tester - Intermediate Level (CSTIL) CSTIL Exam Practice Test

Page:    1 / 14   
Total 25 questions

Question 1

Which of the following are product risks and which are project risks?

a.The navigation through some parts of the website may need to be different from others.

b.Sprint 1 may not be completed on time, leading to a delay to the start of Sprint 2.

c.Text versions of images may not always be possible.

d.There may be a need to buy a capture-replay tool for regression testing.

key member of the team may leave before the Sprints have been completed.



Answer : B

Question 2

Which stage of the Fundamental Test Process will be most affected by the use of user-stories as defined above?



Answer : B

Question 3

Which of the following review types would be recommended at the start of each Sprint, for the reason given?



Answer : C

Question 4

Which of the following methods of test estimation would be most appropriate for each Sprint?



Answer : A

Question 5

Which of the following is the main purpose of an incident tracking process?



Answer : D

Page:    1 / 14   
Total 25 questions