GAQM Certified Software Tester - Intermediate Level (CSTIL) CTIL-001 CSTIL Exam Practice Test

Page: 1 / 14
Total 25 questions
Question 1

Which of the following provides the best example of a product risk leading to a project risk?



Answer : A


Question 2

Which one is a product risk associated with the air quality management system?



Answer : C


Question 3

Which stage of the Fundamental Test Process will be most affected by the use of user-stories as defined above?



Answer : B


Question 4

Which of the following activities should be carried out at the start of this process?



Answer : B


Question 5

Which one of the following test tools would you recommend for the E2E phase.



Answer : C


Question 6

At what point in the test process should you first consider the test environment required for the project?



Answer : B


Question 7

Which of the following methods of test estimation would be most appropriate for each Sprint?



Answer : A


Page:    1 / 14   
Total 25 questions