GAQM PPM-001 Professional in Project Management (PPM) - Standard Package PPM Exam Practice Test

Page: 1 / 14
Total 650 questions
Question 1

Overlapping activities on a project, such as design and construction, is referred to as:



Answer : C


Question 2

An Ishikawa or fishbone diagram is used for which of the following?



Answer : A


Question 3

A project manager has finished the project. He knows that the project scope has been completed and is within cost and time objectives set by management. Management, however, says that the project is a failure, because the original schedule was for 27 weeks and the project was completed in 33 weeks. If the project baseline was 33 weeks, the project is a success because:



Answer : B


Question 4

EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate to complete) the remaining work. Which of the following is a valid formula for calculating EAC?



Answer : A


Question 5

The person in the organization that authorizes the commencement of a project is the

______________?



Answer : B

The project manager executes the project but does not authorize the project. Sponsor authorize the project.


Question 6

Which process group can be performed outside the project's scope of control?



Answer : D


Question 7

Reserve Analysis a technique not used in:



Answer : C

Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as costs in many schedule activity cost estimates. Reserve Analysis a technique not used in Control Costs.


Page:    1 / 14   
Total 650 questions