GAQM Professional in Project Management (PPM) - Standard Package PPM-001 PPM Exam Questions

Page: 1 / 14
Total 650 questions
Question 1

Which of the following documents allows the project manager to assess risks that may require near term action?



Answer : C


Question 2

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?



Answer : C


Question 3

Which tool and technique is used to sequence activities?



Answer : C


Question 4

All the techniques described below can be used to keep a meeting focused except:



Answer : B


Question 5

Your company has just presented its new five-year strategic plan. You have received a new product request from a customer that is in line with the previous five-year strategic plan, but it does not meet the objectives of the new plan. The product description seems to have a valid business driver and to be a straightforward development effort. As project manager, what is the BEST course of action?



Answer : B


Question 6

What is the primary benefit of meeting quality requirements?



Answer : B


Question 7

The sponsor is worried about the seller deriving extra profit on the cost plus fixed fee (CPFF) contract. Each month the sponsor requires the project manager to submit CPI calculations and an analysis of the cost to complete. The project manager explains to the sponsor that extra profits should NOT be a worry on this project because:



Answer : B


Page:    1 / 14   
Total 650 questions