GAQM PPM-001 Professional in Project Management (PPM) - Standard Package PPM Exam Practice Test

Page: 1 / 14
Total 650 questions
Question 1

A procurement management plan is a subsidiary of which other type of plan?



Answer : B


Question 2

When can pre-assignment of project team members occur?



Answer : D


Question 3

Which illustrates the connection between work that needs to be done and its project team members?



Answer : D


Question 4

Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 workdays. What should be your concern?



Answer : B


Question 5

Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?



Answer : A


Question 6

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?



Answer : A


Question 7

Which of the following is a schedule network analysis technique that takes limited resources into account?



Answer : B


Page:    1 / 14   
Total 650 questions