GAQM Professional in Project Management (PPM) - Standard Package PPM-001 PPM Exam Practice Test

Page: 1 / 14
Total 650 questions
Question 1

Which technique is utilized in the Schedule Control process?



Answer : D


Question 2

When communicating with large audiences, which communication method works most effectively?



Answer : D


Question 3

Which process group establishes the total scope of a project?



Answer : B


Question 4

The most effective team motivator is:



Answer : D


Question 5

You are the project manager for a top-secret software project for an agency of the United States government. Your mission-should you choose to accept it-is to complete the project using internal resources. The reason is that finding contractors with top-secret clearances takes quite a bit of time, and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Slowly but surely your programmers are taken off this project and reassigned to the executive director's hot new project. Which of the following type of project ending is this?



Answer : D

Integration occurs when resources, equipment, or property are reassigned or redeployed back to the organization or to another project.


Question 6

What is the minimum a project schedule must include?



Answer : B


Question 7

Which of the following provides a basis for assessing project performance?



Answer : C


Page:    1 / 14   
Total 650 questions