GAQM PPM-001 Professional in Project Management (PPM) - Standard Package PPM Exam Practice Test

Page: 1 / 14
Total 650 questions
Question 1

Which tool or technique is used in Close Procurements?



Answer : D


Question 2

Cost baseline is an output of which of the following processes?



Answer : B


Question 3

Which technique is utilized in the Control Schedule process?



Answer : D


Question 4

Which of the following tools or techniques is used for Estimate Activity Durations?



Answer : D


Question 5

The project scope statement and resource calendars are inputs to which Project Time Management process?



Answer : C


Question 6

To which process is work performance information an input?



Answer : A


Question 7

What happens to a stakeholder's project influence over time?



Answer : B


Page:    1 / 14   
Total 650 questions