GAQM Professional in Project Management (PPM) - Standard Package PPM-001 PPM Exam Practice Test

Page: 1 / 14
Total 650 questions
Question 1

Parametric estimates are based on variables such as:



Answer : B


Question 2

How is scheduled variance calculated using the earned value technique?



Answer : C


Question 3

EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate to complete) the remaining work. Which of the following is a valid formula for calculating EAC?



Answer : A


Question 4

You are a project manager for Dutch Harbor Consulting. Your latest project involves the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Closing process and know that product verification is for what purpose?



Answer : A

Product verification is performed by the buyer and examines all the work of the project and

verifies that the work was completed correctly and satisfactorily.


Question 5

A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here?



Answer : B


Question 6

If two events cannot both occur in a single trial, they are:



Answer : B


Question 7

At which point of the project is the uncertainty the highest and the risk of failing the greatest



Answer : B


Page:    1 / 14   
Total 650 questions