Which three functions are performed by a VSP G1000 Virtual Storage Director (VSD)? (Choose three.)
Answer : A, C, D
DP-Vol LUNs are taken from an HDP pool deployed with 128 disks (16x4D+4D RAID groups). Access is random read.
Which combination of FC paths, LUN Queue Depth, and number of DP-Vols will result in a per-disk queue of 4 within this pool?
Answer : D
Response times in an HDP pool have been increasing consistently with each additional workload during a large scale migration. The response times may become unacceptable with subsequent migrations. The
purchase of additional equipment is an acceptable solution. What are two valid actions in this scenario?
(Choose two.)
Answer : A, C
A high level of writes to external storage is backing up into a VSP G1000 cache, creating a high write pending problem that is affecting other workloads.
Which three actions will help to minimize this problem? (Choose three.)
Answer : A, B, D
Which three statements are true regarding the Hitachi external storage architecture? (Choose three.)
Answer : A, B, D
A customer is considering buying a new VSP Midrange system with iSCSI front-ends. The system will be used to support existing Oracle databases and a new MS Exchange mail system. The existing customer's LAN has enough resources to handle the iSCSI traffic. They have provided the required storage for Oracle and MS Exchange.
What I/O profile information is required to size the VSP system in this scenario? (Choose two.)
Answer : B, D
Which three key metrics are required for sizing applications? (Choose three.)
Answer : A, B, C