Huawei H12-425 HCIP-Data Center Facility Deployment V1.0 Exam Practice Test

Page: 1 / 14
Total 240 questions
Question 1

If the customer load cannot be power-off, what should be taken care when closing the maintenance bypass switch?



Answer : A, B, D


Question 2

On the Current Alarm page of NetEco, filter criteria can't set to search for the required alarms.



Answer : B


Question 3

NetEco can't send work orders to processors.



Answer : B


Question 4

NetEco can mail reports to customers.



Answer : A


Question 5

By setting the mailbox parameters, the NetEco system will send an email to notify the user according to the set rules.



Answer : A


Question 6

Which is not included in the routine maintenance of the ECC800 module?



Answer : D


Question 7

On the NetEco, the door status is always open, we can identify with the faulty by ( ).



Answer : A, B, C