Question 1

The UPS5000-E has strong load adaptability. It does not derate in case of leading/lagging capacitive/inductive loads.



Answer : B


Question 2

How many side panels can be configured at most for one IT cabinet of the Fusion Mod uie2000? ()



Answer : B


Question 3

The DC cable voltage drop must be within ( ).



Answer : A


Question 4

For traditional UPSs, the number of batteries cannot be adjusted/ and the battery maintenance cost is high because one faulty battery can result in replacement of the whole battery string. For the UPS5000-A, the number of batteries can be adjusted between ().



Answer : D


Question 5

Which of the following statements are correct about the UPS5000-E overload capacity? (Multiple Choice)



Answer : A, D


Question 6

For 80 kW IT loads, configuring an 80 kVA UPS can meet the basic requirements.



Answer : B


Question 7

The UPS2000-G series (6 kVA to 20 kVA) supports up to () UPSs in parallel, providing excellent scalability.



Answer : D