IBM C2010-555 Maximo Asset Management v7.6 Functional Analyst Exam Practice Test

Page: 1 / 14
Total 144 questions
Question 1

A company has a requirement to temporarily give a user the privilege to run the application's manual status change actions and specify this in a workflow process.

Which of the following actions would be used?



Answer : A


Question 2

A company has assets at multiple locations that require maintenance. There is a requirement to have a single work order with charges rolled up to a single GL account.

How can that be achieved?



Answer : B


Question 3

A company is using Process Flow Control to ensure the tasks are done in the proper order.

By default, which status indicated the next task to be worked on?



Answer : C


Question 4

Which tab provides a graphical representation of an asset and its relationships?



Answer : B


Question 5

What is the reason to specify asset relationships?



Answer : C


Question 6

A planner needs to combine a number of items to be used regularly that can be tracked by a single item number and issued to work orders.

How can this be achieved?



Answer : B


Question 7

A supervisor is required to report actual work hours by work order number.

With which statuses can this be accomplished? (Choose two.)



Answer : A, B