iSQI ISTQB Certified Tester - Agile Tester CTFL-AT Exam Questions

Page: 1 / 14
Total 80 questions
Question 1

Which of the following is a benefit of a whole-team approach?



Answer : D


Question 2

Which statement about an Agile task board is CORRECT?



Answer : A


Question 3

During a retrospective, which of the following items would be the LEAST effective to generate discussions on process improvement?



Answer : D


Question 4

Which ONE of the following is an example of a typical ''Business-oriented work product''?



Answer : B


Question 5

A calculator application is being developed. The third sprint has been planned to add functionality to the calculator to allow scientific calculations.

Which TWO examples below represent activities that would likely be managed on an agile task board for the third sprint?

1) A task to design the features planned for the next sprint.

2) A task to run an acceptance test for a user story.

3) A task to automate regression tests.

4) A task to participate in training in preparation for the fourth sprint.

5) A task to produce a daily progress report for the agile team members.



Answer : A


Question 6

You are a tester in an agile team. The user story you are due to test is still under development so your tests are blocked. The main issue holding progress on this user story is that the developer's unit tests are constantly failing.

As an agile tester, which of the following actions should you take?



Answer : C


Question 7

Which agile development approach incorporates the following practices:

* a project is divided into iterations called sprints

* each sprint results in a potentially releasable/shippable product?



Answer : D


Page:    1 / 14   
Total 80 questions