Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
* Create a purchase agreement for the subcontracting vendor and add SP-01 as the painting service.
* Create a vendor resource then create a work cell fcr outsourced painting and add the resource to the work cell.
* Create a production flow process activity for the painting work cell and add the component to be painted as a picking activity.
* Create a service term to tie the purchase agreement to the activity.
Does the solution meet the goal?
Answer : B
You need to set up the correct production solution for the assembly are
a. Which solution should you implement?
Answer : D
You produce 100 total units of finished goods. The amount of material used to produce the goods is the equivalent amount of material needed to produce 105 finished goods. The company must track variances in material compared to the original estimated amount You must only use one picking list journal for each production order. You need to post a picking list that accounts for the material required to produce 105 finished goods. What should you do?
Answer : D
You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. This item has the following Lean setup:
* The setup uses a Lean schedule group with a throughput ratio = 2.
* The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1.
* The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8 hour day).
* The throughput is 10 per hour.
You need to set up a Discrete operation to mirror the item's production flow activity.
A customer produces light projection toys for holiday decorations throughout the year. The production process
creates the projections toy at the following work cells stands, main assembly, electric, visuals, and packaging.
visual templates to the warehouse. Each transfer for each vendor must use the same purchase agreement.
You need to configure the subcontracted transfer activity.
What should you do?
A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management.
The company requires that employees register time against each machine on the shop floor.
You need to configure the system so that employees can register time.
Which two configurations must be set up? Each answer represents a partial solution.
NOTE: Each correct selection is worth one point.
You must ensure that the firepit product is available for sale. How should the product be released?
Answer : B