Microsoft MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Exam Practice Test

Page: 1 / 14
Total 207 questions
Question 1

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A client subcontracts production work to a vendor for production operations.

You need to model subcontracting of route operations in production orders.

Solution: Ensure that the service product is stocked and is part of the Bill of Materials.

Does the solution meet the goal?



Answer : B


Question 2

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A client subcontracts production work to a vendor for production operations.

You need to model subcontracting of route operations in production orders.

Solution: Ensure that subcontracting of route operations supports back-flush costing.

Does the solution meet the goal?



Answer : B


Question 3

A company uses Lean manufacturing processes with Kanban boards.

When unexpected transfer jobs occur, the boards do not clear properly.

You need to ensure that the boards clear properly.

What are two possible ways to clear the board? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.



Answer : A, B


Question 4

A company configures master planning to order large and expensive aluminum sheets that are only available at certain times of the year.

The warehouse manager reports that replenishment levels are too high, causing inventory value to be over budget. In addition, the aluminum sheets take up too much space on the shop floor.

You need to configure the appropriate replenishment method.

Which coverage dimension should you use?



Answer : A


Question 5

A company uses Dynamics 365 Supply Chain Management to ship hazardous materials across several countries/regions.

Several products cannot legally be shipped together in the same truck due to the risk of a hazardous chemical reaction if there is an accident.

You need to configure the compatibility groups for the product restrictions.

Which two lists should you configure? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.



Answer : A, E


Question 6

A company implements Dynamics 365 Supply Chain Management.

Due to increased demand and limited space in the work cell area for product L0050, you must subcontract overflow work to another company. You have the following requirements:

Locate a warehouse at the subcontractor building.

Support picking and shipping activity tracking.

Associate costs of transporting materials between the locations in the cost of the finished product.

You need to modify the production flow.

Which three actions should you perform? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.



Question 7

You are a functional consultant for Contoso Entertainment System USA (USMF).

You need to schedule the Material Requirements Planning (MRP) master plan to run nightly at 03:00 (UTC-8).

To complete this task, sign in to Dynamics 365 portal.



Answer : A

You need to configure a batch job to run the master plan nightly.

Create the batch job

Go toNavigation pane > Modules > System administration > Inquiries > Batch jobs.

ClickNew.

In theJob descriptionfield, type a value.

In theScheduled start date/timefield, enter a date and time.

ClickSave.

Create a recurrence

On the Action Pane, clickBatch job.

ClickRecurrence. Use these options to enter a range and pattern for the recurrence.

ClickOK.


https://docs.microsoft.com/en-us/dynamics365/fin-ops-core/dev-itpro/sysadmin/tasks/create-batch-job

Page:    1 / 14   
Total 207 questions