Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert MB-335 Exam Practice Test

Page: 1 / 14
Total 195 questions
Question 1

A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management.

The company requires that employees register time against each machine on the shop floor.

You need to configure the system so that employees can register time.

Which two configurations must be set up? Each answer represents a partial solution

NOTE Each correct selection is worth one point.



Answer : A, B


Question 2

You need to configure production control parameters for liquid cleaning solution manufacturing.

What are two possible ways to achieve this goal? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.



Answer : B, C


https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/formulas-versions

Question 3

You are the lead product design engineer at a plastics manufacturing company.

You implement a new process that uses a single to produce three finished at the same time.

You need to set up the planning items number and formula to correctly to manufacturing the tree items.

Which three actions should you perform? Each correct answer presents part of the solution.



Answer : A, B, C


Question 4

A company uses Process manufacturing for most products and Discrete manufacturing for other products. The company is creating a formula for a new product. The new item will be used to make a name brand product and two generic brand products.

This item has the following requirements:

* Production of the name brand and generic products must use the same formula.

* The company must produce all three items at the same time.

You need to create a produced item that can make two generic items and one main item.

How should you set up the item?



Answer : C


Question 5

A manufacturer uses Dynamics 365 Supply Chain Management to build bicycles.

When manufacturing releases production orders to the warehouse, the warehouse must avoid automatically releasing the bill of materials (BOM) and formula lines. The BOM and formula lines must be manually released later through a batch process.

You need to configure the functionality for the records.

At which two locations should you configure this functionality? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.



Answer : C, E


Question 6

You need to report newly manufactured bicycles as finished products.

Which three options can you use? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.



Answer : C, D, E


Question 7

A company uses engineering change management for process manufacturing operations.

The company discovers that several products were configured with missing master data during the life cycle of the products. You need to configure master data checks for the products.

Which three objects can you configure for data checks? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.



Answer : A, B, D


Page:    1 / 14   
Total 195 questions