You need to plan scheduling for Customer1's order of unscented solution.
What are two possible ways to achieve the goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
Answer : C, E
A company produces energy-efficient LED lighting solutions. Production is dependent on primary and secondary resources.
The primary resource is skilled assembly workers responsible for assembling LED lighting fixtures. The workers can work on only one fixture at a time during production.
The secondary resource is automated LED soldering machines, which typically operate at a 50% load capacity. The machines can work on multiple LED lighting fixtures at the same time.
The company must optimize the allocation of resources to meet customer demands efficiently.
You need to configure the resources to meet the customer demand.
What should you do?
Answer : C
You are the lead product design manage at a Process manufacturing plant.
A formula that produces egg yolks as a by-product. This by-product is added back into inventory at standard cost and can be used in other production batches.
You need to select the by-product cost allocation.
Which cost allocation type should you use?
Answer : D
A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.
Purchase orders for a raw material are created more frequently than needed. This results in missed discounts with the vendor who sells the raw material.
The raw material items have a 30-day lead time. The company is willing to delay sales and production order demand that may consume the raw material for up to 15 days to consolidate purchase orders.
You need to configure the setup to include lead time and consolidate purchase orders.
What should you configure?
Answer : C
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to It. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
* Create a purchase agreement for the subcontracting vendor and add SP-01 as the painting service.
* Create a vendor resource then create a work cell for outsourced painting and add the resource to the work cell.
* Create a production flow process activity for the painting work cell and add the component to be painted as a picking activity.
* Create a server term to tie the purchase agreement to the activity.
Does the solution meet the goal?
Answer : A
The solution does not meet the goal. Here is the explanation:
To create a subcontracting activity for the painting service, you should use the following steps1:
1:Activity-based subcontracting
A manufacturer uses Dynamics 365 Supply Chain Management to build bicycles.
When manufacturing releases production orders to the warehouse, the warehouse must avoid automatically releasing the bill of materials (BOM) and formula lines. The BOM and formula lines must be manually released later through a batch process.
You need to configure the functionality for the records.
At which two locations should you configure this functionality? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
Answer : C, E
A co uses the asset management module in Supply Cham Management. The company has four conveyer systems in the warehouse. A robotic crane moves pallets of products to its conveyer int. Each robotic crane and conveyer line is considered a multilevel asset.
A work order arrives for a conveyer system. A technician completing the work observes that the robotic crane needs a repair. The technician is not qualified to work on the robotic crane.
You need to ensure that the robotic is repaired.
Which two options should you configure? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
Answer : B, D