You need to configure the manufacturing groups for the standard model bicycle and the new limited-edition bicycle for the summer season.
Which object should you use?
Answer : B
A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management.
The company requires that employees register time against each machine on the shop floor.
You need to configure the system so that employees can register time.
Which two configurations must be set up? Each answer represents a partial solution
NOTE Each correct selection is worth one point.
Answer : A, B
You are building the Bill of materials (BOM) for a new production item. The new item has a subcomponent.
Subproduction orders for the subcomponent must be created when estimating production orders.
You need to configure the BOM line to generate sub production orders.
Which BOM line type should you use?
Answer : D
The BOM line type determines how the line is handled during master planning and batch order production1.The Item line type indicates that the item is a material or service that is directly consumed, and that doesn't require further explosion or pegged supply1.When you estimate a production order for an item that has a BOM line with the Item line type, a subproduction order is created for the item2.
The other options are not correct, because they do not generate subproduction orders.The Vendor line type indicates that the item is purchased from a vendor and not produced internally1.The Phantom line type indicates that the item is an intermediate product that is used to simplify the design process and group complex products into engineering modules1.The Pegged supply line type indicates that the item is supplied by another production order or transfer order, and that the supply must be reserved before it can be consumed1.
A company configures master planning to order large and expensive aluminum sheets that are only available at certain times of the year.
The warehouse manager reports that replenishment levels are too high, causing inventory value to be over budget. In addition, the aluminum sheets take up too much space on the shop floor.
You need to configure the appropriate replenishment method.
Which coverage dimension should you use?
Answer : A
A company uses Dynamics 365 Supply Chain Management for Process manufacturing.
You are reviewing the planned production orders for the next two weeks. There are several production orders for the same product. One order is scheduled to run the week after another order.
You need to optimize the planned production orders.
What should you do?
Answer : C
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear on the review screen.
A manufacturing company produces electronic components and devices.
The company has scheduling issues related to using working time calendars in manufacturing.
You need to ensure that the working time calendar is used when manufacturing jobs are scheduled.
Solution: Enable route groups for a capacity job type.
Does the solution meet the goal?
Answer : B
You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.
A machine in the facility is defective and must be closed for repairs for the next two days.
You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?
Answer : C