PeopleCert IASSC Lean Six Sigma - Yellow Belt IASSC Exam Practice Test

Page: 1 / 14
Total 120 questions
Question 1

The Control Plan is created following the finalization of the Measure Phase and can be closed when?



Answer : C


Question 2

An important factor in a viable _________ is to determine who, when and to what level various personnel must be trained to maintain the improvements made to a process.



Answer : C


Question 3

A Lean Principle that states the process of eliminating waste is a continual process requiring one to always be on the lookout for ways to reduce the seven elements of waste is known as ____________ .



Answer : B


Question 4

It is recommended that when beginning a 5S program it be started in a pilot work area for learning and demonstration purposes then it is expended throughout the plant.



Answer : A


Question 5

A ______________ is a graphical presentation of sample data that shows the number of times that a data point is a specific number.



Answer : B


Question 6

The ''Equipment'' category of Root Causes on a Fishbone Diagram would be used primarily used to generate ideas as to which of the following are possible causes for defects?



Answer : D


Question 7

In order to properly draft a Process Map at the start of a project we are told to __________________ from beginning to the end.



Answer : B


Page:    1 / 14   
Total 120 questions