PeopleCert PRINCE 2 Foundation (7th Edition) PRINCE2-Foundation Exam Questions

Page: 1 / 14
Total 476 questions
Question 1

Which is a responsibility of the project board?



Answer : C

One of the key responsibilities of the project board within PRINCE2 is to ensure effective communication with external stakeholders. This involves overseeing the project's strategic direction and ensuring that stakeholder needs, expectations, and communications are properly managed and addressed throughout the project lifecycle.

= PRINCE2 7 Foundation handbook and online resources


Question 2

How many management stages should a PRINCE2 project consist of?



Answer : A

A PRINCE2 project should consist of a start-up stage, an initiation stage, and at least one other management stage to cover the remainder of the project. This structure ensures that the project is properly initiated and planned before entering into a series of management stages where the work is executed and completed, followed by a closing stage. Reference: PRINCE2 Foundation manual, PRINCE2 official resources


Question 3

When does the 'directing a project' process start?



Answer : B

The 'Directing a Project' process in PRINCE2 starts when the request to authorize a project is received. This request usually comes after the initial project setup has been reviewed and there is a need to formally authorize the project to begin detailed planning and execution. This is a crucial step in establishing the governance framework that will guide the project's overall direction.

(PRINCE2 7 Foundation Handbook, AXELOS)


Question 4

When developing a business case, the project manager reviewed the end project report from and previous similar project that stated had been underestimated on the project.

Which principle is being applied by the project manager when reviewing this information?



Answer : A

The principle of 'Learn from experience' in PRINCE2 mandates that project teams should continuously use previous lessons to improve the outcomes of current and future projects. By reviewing end project reports from similar past projects to understand and correct underestimations, the project manager is directly applying this principle to refine and optimize project planning and execution.

= PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation


Question 5

How does the project plan help to support the 'manage by stages' principle?



Answer : C

The project plan supports the 'manage by stages' principle in PRINCE2 by identifying major control points and milestones. These serve as points at which the project board can review progress and decide whether to continue with the project. This principle ensures that the project is manageable, controllable, and that decisions can be made with proper governance at each stage. Reference: PRINCE2 Foundation Handbook, Manage by Stages section.


Question 6

What must be produced to meet the minimum requirements for applying the change theme?



Answer : B

To meet the minimum requirements for applying the Change Theme in PRINCE2, it is essential to maintain detailed records of all decisions taken on issues. This documentation supports the governance of changes, ensuring that all changes and their impacts are managed transparently and effectively throughout the project. Reference: PRINCE2 7 Foundation Handbook and official training materials.


Question 7

The senior user needs to understand how user assurance will support the senior user on the project.



Answer : C


Page:    1 / 14   
Total 476 questions