PeopleCert PRINCE2 Foundation Exam (2017) Exam Practice Test

Page: 1 / 14
Total 296 questions

Question 1

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?



Answer : D

Question 2

Which is a true statement about PRINCE2 event-driven controls



Answer : C

Question 3

Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans



Answer : C

Question 4

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities



Answer : B

Question 5

Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.



Answer : B

Question 6

Which is performed as part of the recommended risk management procedure?



Answer : C

Question 7

Identify the missing words in the following sentence.

Configuration management typically includes [ ? ] as one of the five core activities.



Answer : D

Page:    1 / 14   
Total 296 questions