Question 1

Which is an objective of the Closing a Project process?



Answer : B

The objective of the Closing a Project process in PRINCE2 includes reviewing the performance of the project against its baseline. This ensures that all objectives have been achieved, the project has delivered the required products, and stakeholders are satisfied with the outcomes. It provides a formal closure to the project by ensuring all project work is completed and assessed. Reference: PRINCE2 Foundation manual, PRINCE2 official resources


Question 2

The project manager needs to understand what makes the outputs acceptable to the users.

In which step of the 'planning' technique should this occur?



Answer : A

In the 'planning' technique of PRINCE2, understanding what makes the outputs acceptable to the users occurs during the step of 'Defining and Analyzing the Products.' This step involves detailed discussions about product requirements and specifications to ensure clarity on what the project must deliver for it to be accepted by the users. It sets out the criteria that the products must meet to satisfy the user's needs and expectations.

(PRINCE2 7 Foundation Handbook, AXELOS)


Question 3

Which is a purpose of the business case theme?



Answer : D

The purpose of the Business Case theme in PRINCE2 is to establish a viable investment proposition. It justifies the investment in the project through an ongoing assessment of benefits, costs, and risks, ensuring that the project remains desirable, viable, and achievable throughout its life.

PRINCE2 7 Foundation Source: PRINCE2 Foundation handbook and online resources


Question 4

Which is a purpose of the Closing a Project process?



Answer : C

The purpose of the Closing a Project process is to ensure that the objectives defined in the Project Initiation Documentation (PID) have been achieved. This process involves verifying that the project's deliverables meet the objectives and that the project has fulfilled its purposes as planned. Reference: PRINCE2 Foundation official study guide and materials.


Question 5

Which is a purpose of the Initiating a Project process?



Answer : C

The purpose of the Initiating a Project process is to establish solid foundations for the project, ensuring that there is a clear understanding of the reasons for the project, the benefits expected, and how the delivery will be managed. This foundation is crucial for the successful management and delivery of the project. Reference: PRINCE2 Foundation manual, PRINCE2 official resources


Question 6

Which action should the project manager take when reviewing progress to assess the 'health' of a stage?



Answer : D

When reviewing the progress to assess the 'health' of a stage, the project manager should focus on how issues are being managed. Identifying whether issues are resolved timely or remain unmanaged is crucial for maintaining the health of the project stage and ensuring that risks do not escalate and affect the project's success.

PRINCE2 7 Foundation handbook on stage management and issue resolution.


Question 7

Which is a purpose of the 'closing a project' process?



Answer : B

The purpose of the 'closing a project' process in PRINCE2 is to verify that all project objectives have been delivered and that the project has nothing more to deliver. It ensures that all project products have been handed over and accepted, and evaluates the performance of the project against its baselines. Reference: PRINCE2 Foundation Handbook, Closing a Project Process section.