Why does PRINCE2 recommend three different levels of plans?
Answer : B
Which is a purpose of the Initiating a Project process?
Answer : C
What needs to be in place to ensure effective issue and change control?
Answer : A
Which is a Benefits Review Plan used to assess?
Answer : A
What theme defines and implements the means by which the project will verify that products meet business requirements?
Answer : D
Identify the missing words in the following sentence.
When planning the next stage, the Project Manager needs to review and, if necessary, update the [ ? ] with regard to external resources or suppliers.
Answer : D
Which is a true statement about acceptance criteria?
Answer : D