PMI Certified Associate in Project Management CAPM Exam Practice Test

Page: 1 / 14
Total 1330 questions
Question 1

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?



Answer : A


Question 2

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?



Answer : D


Question 3

The diagram below is an example of a:



Answer : A


Question 4

Which of the following lists of tools and techniques is used when conducting procurements?



Answer : C


Question 5

A tool and technique used during the Collect Requirements process is:



Answer : A


Question 6

What is a tailoring consideration for the application of Project Risk Management processes?



Answer : A


Question 7

When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?



Answer : C


Page:    1 / 14   
Total 1330 questions