PMI Certified Associate in Project Management PMI CAPM Exam Practice Test

Page: 1 / 14
Total 1135 questions
Question 1

What key component of the project charter defines the conditions for dosing a project phase?



Answer : C

Question 2

What organizational process asset (OPA) might impact a project's outcome?



Answer : A

Question 3

What tool or technique will establish expected behaviors for project team members?



Answer : A

Question 4

What is the primary purpose of Project Scope Management?



Answer : C

Question 5

A project team identifies defects that will require a modification to a tool's functionality. What process should the project manager follow to obtain stakeholder buy-in?



Answer : C

Question 6

What is the common factor among portfolios, programs, and projects, regardless of the hierarchy within an organization?



Answer : A

Question 7

A software development team is pulling work from its backlog to be performed immediately as they become available. What emerging practice for project scheduling is the team using?



Answer : A

Page:    1 / 14   
Total 1135 questions