PMI Certified Associate in Project Management CAPM Exam Questions

Page: 1 / 14
Total 1305 questions
Question 1

An international company that is starting to practice an adaptive approach has several development teams located globally. They are having problems with multiple time zones and repetitive project schedule slippage.

What effective tools should the project teams use to collaborate?



Answer : A


Question 2

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?



Answer : B


Question 3

Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?



Answer : D


Question 4

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?



Answer : A


Question 5

A project is at the closing stage. The project manager asks the team to perform closing functions at the next meeting. Which two procedures will the project team perform? (Choose two)



Answer : A, B


Question 6

A tool or technique used in the Control Procurements process is:



Answer : B


Question 7

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:



Answer : C


Page:    1 / 14   
Total 1305 questions