PMI Certified Associate in Project Management PMI CAPM Exam Practice Test

Page:    1 / 14   
Total 789 questions

Question 1

Which of the following is a category of organizational process assets?



Answer : D

Question 2

Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?



Answer : D

Question 3

Which of the following tasks focuses on decomposing work packages?



Answer : C

Question 4

Which task will a project manager undertake while conducting Project Resource Management?



Answer : A

Question 5

A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.

Which technique is the project manager using?



Answer : C

Page:    1 / 14   
Total 789 questions