PMI CAPM Certified Associate in Project Management PMI CAPM Exam Practice Test

Page: 1 / 14
Total 1250 questions
Question 1

The process to ensure that appropriate quality standards and operational definitions are used is:



Answer : B


Question 2

Which tool or technique is effective in a project in which the deliverable is not a service or result?



Answer : D


Question 3

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?



Answer : B


Question 4

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?



Answer : C


Question 5

What document gathers all of the lessons learned at the end of a phase or project



Answer : D


Question 6

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?



Answer : D


Question 7

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?



Answer : B


Page:    1 / 14   
Total 1250 questions