PMI Certified Associate in Project Management CAPM Exam Questions

Page: 1 / 14
Total 1305 questions
Question 1

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?



Answer : C


Question 2

Which tool or technique is used in the Estimate Costs process?



Answer : C


Question 3

An output of the Validate Scope process is:



Answer : D


Question 4

Which three processes are generally included in risk management? (Choose three)



Answer : B, C, D


Question 5

An example of a group decision-ma king technique is:



Answer : B


Question 6

The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?



Answer : B


Question 7

On which type of project.... only after the final iteration?

On wtiich type of project lite cycle is ihe deliverable produced trough a series of ileralrons considering thai the deliverable ts completed only after the Imal iteration?



Answer : B


Page:    1 / 14   
Total 1305 questions