PMI Certified Associate in Project Management PMI CAPM Exam Practice Test

Page: 1 / 14
Total 1135 questions
Question 1

A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?



Answer : D


Question 2

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take to account for risk management n this environment'



Answer : D


Question 3

What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?



Answer : B


Question 4

What three strategies are used to respond to threats?



Answer : A


Question 5

What is an example of a technical project management skill?



Answer : A


Question 6

What type of stakeholder is part of a project manager 's sphere of influence on a project?



Answer : B


Question 7

What estimating technique is used when there is limited information?



Answer : A


Page:    1 / 14   
Total 1135 questions