PMI Certified Associate in Project Management PMI CAPM Exam Practice Test

Page: 1 / 14
Total 1135 questions
Question 1

A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?



Answer : D


Question 2

What estimating technique is used when there is limited information?



Answer : A


Question 3

During what project management process does the project manager invest the most effort into creating the work breakdown structure (WBS)?



Answer : C


Question 4

What statement describes the function or responsibility of a project manager?



Answer : B


Question 5

In what type of organizational structure does a project manager develop their role and work with a team assigned by job function?



Answer : A


Question 6

Select two key benefits of the Control Procurements process



Answer : B, D


Question 7

For what project management process is work performance information an output?



Answer : A


Page:    1 / 14   
Total 1135 questions