PMI Certified Associate in Project Management CAPM Exam Practice Test

Page: 1 / 14
Total 1305 questions
Question 1

A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to determine if the solution provides the functionality for typical usage by a stakeholder with in-depth business knowledge.

Which evaluation technique is most effective for this situation?



Answer : C


Question 2

A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?



Answer : C


Question 3

In which type of organization does the project manager have the maximum influence



Answer : B


Question 4

The project manager needs to review the templates in use. The templates are part of the:



Answer : C


Question 5

Which of the following is TRUE about most project life cycles?



Answer : B


Question 6

Which of the following are outputs from the process of creating a work breakdown structure (WBS)?



Answer : B


Question 7

Which activity is an input to the Conduct Procurements process?



Answer : A


Page:    1 / 14   
Total 1305 questions