PMI Agile Certified Practitioner PMI-ACP Exam Practice Test

Page: 1 / 14
Total 482 questions
Question 1

An executive sponsor of a new scrum team actively attends scrum ceremonies How does this benefit the team?



Answer : D


Question 2

A scrum team is working together virtually. One of the team members sends a daily email to the other team members listing impediments that they find. During retrospective meetings, the team member complains that their colleagues fail to take actions on the impediments.

How should the team address this issue?



Answer : C


Question 3

An agile team has started to worry because lately they have seen an increase in the number of issues. There seems to be a large variance in the quality of the work items delivered. The team now realizes that a shared understanding of quality may not exist among team members.

What should the team do?



Answer : C


Question 4

A client has provided their requirements and deadline to the project team. The requirements are confusing, and the team is frustrated.

What should the team's servant leader do?



Answer : C


Question 5

What should a Scrum Master do when one team member falls behind in their tasks?



Answer : C


Question 6

A project's first iteration contains item A and its second iteration contains item B The first iteration is behind schedule, which will impact the second iteration. Since items A and B are similar, a team member suggests beginning the design of item B.

What should the agile practitioner do?



Answer : C


Question 7

A newly formed, colocated team is participating in daily standups, but is otherwise working largely as individual contributors. This has resulted in misalignment of activities. Planned velocity is being met.

What should the agile practitioner do?



Answer : A


Page:    1 / 14   
Total 482 questions