PMI Agile Certified Practitioner PMI-ACP Exam Practice Test

Page: 1 / 14
Total 482 questions
Question 1

A servant leader is leading a high-visibility project to deliver a new product. The servant leader has been able to build a cross-functional team and create a team space where the team is collocated. The servant leader started receiving frequent visits from a company director, who continually asks a specific team member questions about project progress. The conversations are distracting the team from their goal.

What should the servant leader do?



Answer : A


Question 2

What can an agile team use to prioritize stories?



Answer : A


Question 3

An agile development team is working on a digital transformation project and is facing challenges in obtaining consistent feedback from stakeholders who are dispersed around the world. The product owner is under pressure as this lack of engagement has led to prolonged decision-making cycles and has adversely affected the outcomes of sprints.

How should the team improve stakeholder engagement to help ensure timely feedback and better decision-making? (Refer to Stakeholder Power/Interest Grid)



Answer : A


Question 4

A new stakeholder has recently joined a project. During a meeting with the scrum master, the new stakeholder tries to understand the status of the project and the remaining tasks for completion.

How should the scrum master inform the new stakeholder?



Answer : A


Question 5

What should a learn consider when calculating the effort needed to complete a product backlog?



Answer : D


Question 6

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns "To do," "In progress," "Ready to be tested," "Test in progress," and "Done." Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of "Ready to be tested" work items has been building up.

What should the team do to improve its speed of delivery?

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns "To do," "In progress," "Ready to be tested," "Test in progress," and "Done." Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of "Ready to be tested" work items has been building up.

What should the team do to improve its speed of delivery?



Answer : A


Question 7

An agile team is building a training safety video based on current government regulations. The agile coach knows the regulations are likely to change before the release date.

How should the agile coach address this change?



Answer : C


Page:    1 / 14   
Total 482 questions