PMI Professional in Business Analysis Exam Practice Test

Page: 1 / 14
Total 200 questions
Question 1

The sales team of a company has won a time-and-malerial project. The business analyst discovers that the sales team has underestimated the required budget and schedule

Which course of action should the business analyst take?



Answer : C


Question 2

Prior to the design phase, the project team needs to conduct a requirements review with the customer. To prepare for the review, it would be best for the team to:



Answer : C


Question 3

A business analyst is documenting the acceptance criteria to suppon a minor modification in a user portal The analyst submits the criteria for review, but it is deemed incomplete and returned.

What could have caused the documentation to be returned?



Answer : B


Question 4

To reduce the amount of time and effort needed to create a product specification for a project, the business analyst plans to reuse:



Answer : A


Question 5

A business analyst is attempting to elicit requirements on a current project. The business subject matter experts (SMEs) from various departments in the company question how the solution will work with their various systems.

Which modeling technique should the business analyst use to depict how the solution will work with all of the company's systems?



Answer : B


Question 6

Company A has set aside capital to invest in an upgrade to their scheduling system Documentation of the current structure was presented to the business analyst However, the description of certain steps are not documented clearly, and the business analyst has not been allowed to inspect the existing system. During elicitation. the business analyst asked questions of the schedulers as they performed functions in order to gain an understanding of the process.

Which type of elicitation technique did the business analyst use in this instance?



Answer : D


Question 7

A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting The stakeholder insists that these requirements must be taken into account despite time and budget constraints.

What is the most effective way to manage this situation?



Answer : D


Page:    1 / 14   
Total 200 questions