PMI-RMP PMI Risk Management Professional Exam Practice Test

Page: 1 / 14
Total 228 questions
Question 1

During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?



Answer : B


Question 2

In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.

What should the risk manager do?



Answer : C


Question 3

While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated.

What should the risk manager do to manage this risk?



Answer : C


Question 4

One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.

Which risk response strategy is the program manager using in this scenario?



Answer : D


Question 5

An organization is embarking on a multi-million-dollar project with numerous identified risks. What should the project risk team do to navigate the risks on this project?



Answer : C


Question 6

A project team's manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (Refer to the email exhibit).

How many total story points is the entire initiative?



Answer : A


Agile estimation techniques suggest using story points to estimate the effort required for backlog items.

The PMI Agile Practice Guide explains that story points represent the complexity, effort, and risk associated with a user story.

Agile teams use story point estimation to gauge work effort without associating it with time directly.

This approach ensures that the team has a clear understanding of the overall workload and can manage risks effectively.

Question 7

The project sponsor asks the project manager about the accuracy of the project dat

a. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?



Answer : D


Page:    1 / 14   
Total 228 questions