PMI Risk Management Professional Exam Practice Test

Page: 1 / 14
Total 273 questions
Question 1

Joan is a project management consultant and she has been hired by a firm to help them identify risk events within the project. Joan would first like to examine the project documents including the plans, assumptions lists, project files, and contracts. What key thing will help Joan to discover risks within the review of the project documents?



Answer : B


Question 2

Harry is the project manager of the MMQ Construction Project. In this project, Harry has identified a supplier who can create stained glass windows for 1,000 window units in the construction project. The supplier is an artist who works by himself, but creates windows for several companies throughout the United States. Management reviews the proposal to use this supplier and while they agree that the supplier is talented, they do not think the artist can fulfill the 1,000 window units in time for the project's deadline. Management asked Harry to find a supplier who can fulfill the completion of the windows by the needed date in the schedule. What risk response has management asked Harry to implement?



Answer : A


Question 3

Mary is the project manager of PKT project. In Mary's project there are certain enterprise environmental factors that require Mary to use modeling and simulation techniques to predict the likelihood of achieving cost and schedule objectives in the project. Mary is using a technique for which the cost estimates are chosen at random for each iteration of the analysis, such as pessimistic, most likely, and worst-case scenarios. What type of analysis is Mary using in this project?



Answer : D


Question 4

You work as a project manager for BlueWell Inc. Your project is running late and you must respond to the risk. Which risk response can you choose that will also cause you to update the human resource management plan?



Answer : C


Question 5

Gary is the project manager of the MMQ project for his company. He is working with his project team to plan the risk responses for his project. Sarah, a project team member, does not understand the process that Gary is using to plan the risk responses. Which approach is the preferred method to address project risks and the risk responses?



Answer : D


Question 6

Mike is the project manager of the NNP Project for his organization. He is working with his project team to plan the risk responses for the NNP Project. Mike would like the project team to work together on establishing risk thresholds in the project. What is the purpose of a risk threshold?



Answer : A


Question 7

Mary is a project manager in her organization. On her current project she is working with her project team and other key stakeholders to identify the risks within the project. She is currently aiming to create a comprehensive list of project risks so she is using a facilitator to help generate ideas about project risks. What risk identification method is Mary likely using?



Answer : A


Page:    1 / 14   
Total 273 questions