PMI Risk Management Professional PMI-RMP Exam Questions

Page: 1 / 14
Total 278 questions
Question 1

A project team has failed to complete an important project milestone on time. The team was counting on an external provider to deliver key equipment on a specific date but the provider was delayed.

What should the risk manager have done to prevent missing the milestone?



Answer : B

Identifying and analyzing assumptions is crucial in risk management because assumptions often hide potential risks. PMBOK Guide states:

'During risk identification, it is important to identify and document assumptions and assess their validity... Assumptions may prove to be incorrect, resulting in project risk.'

--- PMBOK Guide, 6th Edition, Section 11.2

This proactive analysis helps uncover hidden risks and plan for contingencies.


PMBOK Guide, 6th Edition, Section 11.2

Question 2

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?



Answer : B


Question 3

A project's design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.

What should the project manager have done differently?



Answer : D

The project manager should have performed risk identification exercises for the full lifecycle of the project, including the construction phase, to ensure that all potential risks were identified and addressed in the risk register.

Risk identification is the process of determining the risks that may affect the project and documenting their characteristics. Risk identification should be performed throughout the project lifecycle, as new risks may emerge or change over time. Risk identification should also consider all aspects of the project, such as scope, schedule, cost, quality, resources, stakeholders, and procurement. By performing risk identification exercises for the full lifecycle of the project, the project manager could have identified and planned for the potential risks associated with the construction phase, such as delays, material shortages, quality issues, or safety hazards. This would have helped to prevent or mitigate the impact of the risk event that occurred, and to ensure that the risk register is updated and comprehensive. Performing a Monte Carlo sensitivity analysis, adding generic construction risks, or reviewing the assumptions/exclusions register are not sufficient or effective ways of identifying the specific risks that may affect the project during the construction phase.These are either tools for risk analysis, risk response planning, or project initiation, but not risk identification.Reference: PMI-RMP Certification Handbook1, page 9; PMBOK Guide, pages 397-398.


Question 4

The project manager wants to use an objective method to evaluate the key project risks and develop response plans.

What action should the risk manager propose?



Answer : C

The action that the risk manager should propose is to ask the team to prepare a Monte Carlo analysis. This is a statistical technique that can be used to model the probability of different outcomes in a project. By performing a Monte Carlo analysis, the project manager can objectively evaluate key project risks and develop response plans based on this analysis.

A Monte Carlo analysis is a simul-ation technique that uses probability distributions and random sampling to model the possible outcomes of a project risk event. It can help the project manager to evaluate the key project risks and develop response plans based on the expected value, standard deviation, and confidence intervals of the results. A Monte Carlo analysis can also provide information on the probability of achieving the project objectives, such as cost, schedule, and quality.A Monte Carlo analysis is an objective method because it does not rely on subjective judgments or opinions, but on mathematical calculations and statistical data.Reference: PMBOK Guide, 6th edition, Section 11.5.2.3, Monte Carlo Analysis1


Question 5

A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?



Answer : D

The project manager should consider stakeholders' positions and opinions regarding the project's output when engaging stakeholders. This approach helps to address stakeholders' concerns, expectations, and potential objections, and it can lead to better decision-making and more successful project outcomes. It is important for the project manager to maintain open communication with stakeholders and to be responsive to their needs and perspectives.

According to the PMI Risk Management Professional (PMI-RMP) Examination Content Outline, one of the tasks under the domain of stakeholder engagement is to ''engage stakeholders by communicating with them to understand their positions and opinions regarding the project's output, and to ensure that their interests are considered in the risk management process'' (Task 1.3). This implies that the project manager should consider stakeholders' perspectives and expectations when engaging them, and not ignore, exclude, or impose on them. Therefore, option D is the correct answer.

Option A is incorrect because not all stakeholders need to be involved in the project's governance, which is the set of policies, processes, and procedures that define how the project is managed and controlled. The project's governance should be determined by the project sponsor and the project management office (PMO), and only include those stakeholders who have authority and responsibility for the project's success.

Option B is incorrect because communicating response strategies to all stakeholders is not a stakeholder engagement activity, but a risk communication activity. The project manager should communicate response strategies to the relevant stakeholders who are assigned to implement or monitor them, and not to all stakeholders indiscriminately.

Option C is incorrect because ignoring any risks beyond stakeholders' tolerance is not a stakeholder engagement activity, but a risk attitude activity. The project manager should identify and assess all risks that may affect the project's objectives, regardless of stakeholders' tolerance levels. The project manager should also consult with stakeholders to determine their risk appetite, threshold, and attitude, and use this information to prioritize and respond to risks accordingly.


Question 6

During a project's planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.

What should the risk manager document as the risk trigger?



Answer : C

A risk trigger is a specific event or condition that signals that a risk is about to occur or has occurred. PMBOK Guide clarifies:

'Risk triggers (sometimes called warning signs) are indicators or symptoms that a risk event is about to occur. The risk register should include identified triggers for each risk.'

--- PMBOK Guide, 6th Edition, Section 11.2.3.1

Thus, documenting the specific event or condition (such as the supplier missing a delivery deadline) is the correct approach.


PMBOK Guide, 6th Edition, Section 11.2.3.1

Practice Standard for Project Risk Management, PMI, Section 5.3

Question 7

A highly complex project is about to start Considering that many changes and new information will arise as the work moves forward, key stakeholders are anxious about not addressing risks on time

What should the risk manager do in this situation?



Answer : D

In highly complex projects where changes and new information are expected to arise continually, it's crucial to implement a dynamic and frequent risk management process. This approach ensures that risks are identified, assessed, and addressed promptly as they emerge throughout the project lifecycle. By regularly updating risk assessments and involving key stakeholders in ongoing risk discussions, the project team can maintain a proactive stance, effectively mitigating potential issues before they escalate. This continuous engagement fosters transparency and reduces stakeholder anxiety by demonstrating a commitment to managing uncertainties actively.

PMI Risk Management Study Guide Reference:

The importance of a dynamic risk management process is emphasized in the PMI-RMP Exam Preparation Study Guide, which highlights the need for continuous risk assessment and stakeholder engagement to adapt to evolving project conditions.


Page:    1 / 14   
Total 278 questions