PMI-RMP PMI Risk Management Professional Exam Practice Test

Page: 1 / 14
Total 274 questions
Question 1

During project implementation, a risk manager wants to determine the effectiveness of risk response plans and which risk will have an impact on the project outcome. Which analysis should the risk manager do?



Answer : A


Question 2

The sponsor of a construction project is upset about the results of the risk management team. The sponsor believes the team did not properly identity the risks that could affect the project. The team did manage the risks however, some of the risk response strategies created secondary risks.

What should the risk management team have done to manage this situation?



Answer : C


Question 3

When performing a risk analysis, a risk manager identifies not only negative risks but also positive risks, which might bring added value to the project. What should the risk manager do next?



Answer : B


Question 4

A risk manager has recommended an increase of 7% to the risk threshold to avoid failure of a challenging new initiative. What should the risk manager do next?



Answer : B


Question 5

A risk manager had to mitigate delay risks in the delivery of a component in a manufacturing project by procuring from an alternate vendor with shorter lead times. This has led to another risk because the project team may need additional training on how to install this specific component.

What should the risk manager do?



Answer : D


Question 6

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the 10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of 5% and reports on the basis of any variance outside that range.

How should the risk manager respond?



Answer : B


Question 7

The major investor in a road construction project is constantly asking project team members for information about the project's execution. This has resulted in the project team working 20% of their day preparing project reports for the stakeholders.

What should the risk manager do to enhance the project team's approach to risk reports?



Answer : B, B


Page:    1 / 14   
Total 274 questions