Which of the following processes involves the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress and performance as well as to forecast the project results?
Answer : B
The report performance process is used for gathering and distributing performance
information. It consists of status reports, progress
measurements, and forecasts. The report performance process contains the periodic collection and
analysis of baseline versus actual data to
understand and communicate the project progress and performance as well as to forecast the
project results.
Answer option A is incorrect. Identify stakeholder process is used to identify all people or
organizations impacted by the project and document
relevant information regarding their interest, involvement, and impact on project success.
Answer option C is incorrect. Plan communication is the process of determining the project
stakeholder information needs and defining a
communication approach.
Answer option D is incorrect. Stakeholder analysis is the identification of stakeholder needs, wants
and expectations. It involves the
documentation, prioritization, and quantification of the needs to help define the project scope.
Stakeholders' interests may be positively or
negatively affected by execution or completion of the project and they may also exert influence over
the project and its deliverables.
Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of the following is the best example of apportioned effort?
Answer : B
Apportioned effort is effort applied that you cannot subdivide into work packages, but it is related to, usually in a supportive role, to the completion of the project work packages. The project management overhead, such managing the project work, is an example of apportioned effort. Apportioned effort (AE) is the effort that is applied to the project-related work that cannot be easily and readily divided into discrete efforts for those tasks, but which is associated in a direct proportion to the discrete work efforts that are capable of being measured. The presence of apportioned effort relies particularly on the performance of further efforts. Answer option C is incorrect. This is an example of discrete effort. Answer option A is incorrect. This is an example of a scope change that has not been approved. Answer option D is incorrect. This is an example of a scheduling technique.
You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?
Answer : B
The best answer is simply an exception report.
An exception report refers and documents the major mistakes, mishaps, and goofs. In other words, it itemizes the important and critically significant piece of documentation that is vital to the proper and effective functioning of a project. It does not document what has gone right, but rather documents what has gone wrong. Answer option C is incorrect. A performance management report is not a valid project management report. Answer option A is incorrect. The question is asked a out cost and schedule so this answer would not be appropriate for both the cost and the schedule. Answer option D is incorrect. The question is asked about cost and schedule so this answer would not be appropriate for both the cost and the schedule.
You work as the project manager for Blue Well Inc. You are working with your project team to schedule the days the project work will take place. You have created a project network diagram as shown in the figure:

Based on this diagram, find out the earliest day on which Activity G can be started.
Answer : D
The earliest Activity G can start is Day 17. This is because activities A, D, C, and F must
all be completed before Activity G can start.
Answer option A is incorrect. Day 13 does not account for Activity F since Activity F is also a
predecessor to Activity G.
Answer option C is incorrect. Day 22 is the earliest Activity G can finish.
Answer option B is incorrect. Day 7 is not a valid answer.
Ben is the project manager for his organization. His project has 26 stakeholders this week and will have five additional stakeholders next week. How many more communication channels will Ben's project have next week?
Answer : A
Ben's project will have 140 more communication channels because of the five additional stakeholders. To solve the question, you will need to find the current stakeholder communication channels first, which is (26*25)/2= 325, and then find the difference of the number of channels for the five additional stakeholders. You can use the formula of N(N-1), where N is the number of stakeholders. In this example, the formula would read: Total number of communication channels that Ben will have next = ((31*30)/2)-((26*25)/2 =140 Answer option D is incorrect. Five is the number of additional stakeholders. Answer option B is incorrect. 10 is the number of communication channels among just five stakeholders. Answer option C is incorrect. 325 is the number of current communication channels.
Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?
Answer : C
Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in
sequence. It is shortening the project schedule without reducing the project scope. It does not add any additional labor but it can introduce project risks. Answer option D is incorrect. Removing things from the project scope can reduce the project duration, but it will not satisfy the requirements the stakeholders have identified. Answer option A is incorrect. Resource leveling can actually increase the project duration. Answer option B is incorrect. Crashing can reduce the project duration but it increases the labor expense, something the stakeholders won't approve.
Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?
Answer : C
According to the PMBOK, Gina will not need the WBS directly, but will rely on the scope baseline.A Work Breakdown Structure (WBS) in project management is a tool that defines a project and groups the project's discrete work elements in
a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control. Answer option A is incorrect. The scope baseline is an input to define the project activities. Answer option D is incorrect. Enterprise environmental factors are an input to define the project activities. Answer option B is incorrect. Organizational process assets are an input to define the project activities.