PMI Scheduling Professional PMI-SP Exam Questions

Page: 1 / 14
Total 326 questions
Question 1

You are the project manager of the GHY Project. This project is scheduled to last for one year and

has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are up

posed to be at your second milestone which accounts for half of the project completion. There have

been some errors in the project which has caused you to spend $2,073,654. What is this project's

schedule variance?



Answer : C

The schedule variance can be found by subtracting the planned value from the earned

value. In this instance, it is $2,025,000 minus

$2,250,000.

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that

the schedule is ahead or behind what

was planned for this period in time. The schedule variance is calculated based on the following

formula:

SV = Earned Value (EV) - Planned Value (PV)

If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater

than 0 shows that the project is ahead of

the planned schedule. A value of 0 indicates that the project is right on target.

Answer option B is incorrect. This is the cost variance for the project.

Answer option A is incorrect. 10 percent is not a valid answer.

Answer option D is incorrect. This is not a valid variance for this question; variances are typically

negative numbers.


Question 2

You are the project manager for your organization. Your current project has a schedule variance of -

$37,500 and a schedule performance index of 0.94. What do these values mean in regard to project

performance?



Answer : D

A schedule variance is found by subtracting the planned value from the earned value. A

-$37,500 schedule variance is considerable for most

projects, but combined with a schedule that is six percent off schedule is more serious. The size of

the project, however, and the defined

project budget, needs to be determined to evaluate how serious the variance is.

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that

the schedule is ahead or behind what

was planned for this period in time. The schedule variance is calculated based on the following

formula:

SV = Earned Value (EV) - Planned Value (PV)

If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater

than 0 shows that the project is ahead of

the planned schedule. A value of 0 indicates that the project is right on target.

Answer option B is incorrect. This project is not performing well based on the given information.

Answer option A is incorrect. This project is likely to be late, but we do not know how costs are

performing in this question.

Answer option C is incorrect. There is not enough information to determine how well the project is

performing from this answer.


Question 3

Sam works as a project manager for BlueWell Inc. Which of the following processes will he use for selecting a scheduling method, scheduling tool, incorporating project specific data within that scheduling tool to develop a project specific schedule model, and generating project schedule?



Answer : C

The schedule development process is used for selecting a scheduling method,

scheduling tool, incorporating project specific data within that

scheduling tool to develop a project specific schedule model, and generating project schedule.

Schedule development is the process of

analyzing activity sequences, durations, resource requirements, and schedule constraints to create

the project schedule. Inserting the

activities, durations, and resources into the scheduling tool generates a schedule with planned dates

for completing the project activities. The

goal of the schedule development is to form the processes such that the stakeholders can use it in

the creation of the project. Schedule

development consists of two main sections:

ArticlesItemsReportsHelp

1.Input and Data: The starting point for any schedule is the input of information developed during

the planning process.

Define schedule scope

Breakdown structure relationships

Schedule specification

Feedback from stakeholders

Cost estimate model

2.Creating Schedule: This process provides basic knowledge in an outline structure for a study of the

means, methods, and tools

necessary for the project schedule development process.

Types of schedules

Activities

Durations

Relationships

Constraints and calendars

Cost and resource loading

Schedule quality analysis and compliance review

Schedule basis documentation

Answer option B is incorrect. Schedules maintenance is a method to account progress and to

forecast trends, progress, and completion.

Schedules are used to manage successful execution of projects. A schedule models the plan using

resources and execution strategy to gather

the project objectives. Periodic updates are undertaken to determine the actual progress achieved.

Information obtained in the updating

process, along with trend analysis and forecast of future progress, is reported to stakeholders. These

progress updates include schedule

maintenance to account for nominal changes to the execution plan. Depending upon the nature of

change, the schedule and assumptions

upon which the schedule was based significantly change. The schedule must be re-examined and

updated, as necessary, to develop a new

baseline for measuring further progress.

Schedule maintenance consists of the following elements:

Baseline Schedule

Tracking Schedule Progress

Cost and Resource Management

Schedule Change Management

Acceleration

Schedule Maintenance Feedback

Answer option D is incorrect. Perform Integrated Change Control is the process of reviewing all

change requests, approving changes, and

controlling changes to the deliverables and organizational process assets in a project. Perform

Integrated Change Control has to do with

influencing the things that cause change, determining that the change is required or has happened,

and managing the change.

Answer option A is incorrect. Constructability analysis is a process that starts in the initial planning

phases and persists all over the entire

planning cycle and into the implementation phase of the project. Constructability analysis during the

planning process examines the methods

and cost of installed equipment and materials, technology, site conditions, resources, and related

infrastructure.

The benefit of constructability analysis is to reduce both the time and cost of a project.

Constructability analysis is repeatedly performed

throughout the life-cycle of a project in order to optimize cost, plan, and schedule while mitigating

risk. It is a very important process that

needs to be performed early in planning to allow alternatives to be considered and integrated into

the design.


Question 4

George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule. What value should George report in this instance?



Answer : B

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that the schedule is ahead or behind what was planned for this period in time. The schedule variance is calculated based on the following formula: SV = Earned Value (EV) - Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target. The earned value in this instance is forty percent of the project budget, $778,000, and the planned value is $398,000 because George is to be fifty percent done at the end of the second quarter, as the work is spread evenly across all quarters. The schedule variance is -$77,800 for the project. Answer option A is incorrect. .96 represents the cost performance index. Answer option C is incorrect. -$34,500 represents the project's variance at completion if the project continues as is. Answer option D is incorrect. -$13,800 is the cost variance for the project.


Question 5

You are the project manager for your organization. You have recently noted some risks associated

with some of the activities in your project. These risks can have schedule and costs impacts on your

project and you need to address the risks through qualitative and quantitative analysis to confirm

the depth of possible impact. Where should you document the risk information concerning the

activities in your project schedule?



Answer : C

The project risks are documented in the risk register - including the probability and

impact information. The risk register is an output of the

Identify Risks process.

Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk

analysis, and risk response planning.

Description, category, cause, probability of occurring, impact on objectives, proposed responses,

owner, and the current status of all identified

risks are put in the risk register.

Answer option A is incorrect. The risk management plan addresses that how risks will be identified,

monitored, and controlled.

Answer option D is incorrect. The activity attributes information is needed, but risks are not part of

the activity attributes.

Answer option B is incorrect. The schedule management plan addresses how the schedule will be

created, executed, and controlled.


Question 6

You are the project manager of the NHQ Project and are trying to determine which seller you should choose for the project. You have received proposals from six vendors and they are all very good proposal, qualified to complete the project work, and the prices are close to the same. You would like to create method of ranking each vendor based and assign a score value to several different categories. Because the project is a high-profile project, you have assigned 25 points to experience and 10 points for all of the other categories to judge the vendors. This is considered what type of source selection process?



Answer : D

This is an example of a weighting system as the values you're measuring are weighted towards

experience.

Answer option B is incorrect. A preferred vendors list describes the vendors you're allowed to

choose from in the organization.

Answer option A is incorrect. A screening system sets qualifiers in place, such as the vendor must

have a PMP on staff, in order to qualify for

the project.

Answer option C is incorrect. The benefits-cost analysis defines the total number of benefits to the

number of costs the project requires. .


Question 7

Joseph works as the project manager of the NHQ Project. He has created the project network diagram as shown in the figure:

Based on the network diagram, find out which path is the critical path for this project?



Answer : D

The critical path is the path with the longest duration to complete the project. It has no float and

shows the earliest completion date and the

latest completion date for the project. In this example, path ACFIJ takes 27 days and is the critical

path.

ACFIJ= A(4)+C(8)+F(4)+I(7)+J(4)= 27

A critical path is the sequence of project activities, which add up to the longest overall duration. This

determines the shortest time possible to

complete the project. Any delay of an activity on the critical path directly impacts the planned

project completion date (i.e. there is no float on

the critical path). A project can have several, parallel, near critical paths. An additional parallel path

through the network with the total

durations shorter than the critical path is called a sub-critical or non-critical path.

These results allow managers to prioritize activities for the effective management of project

completion, and to shorten the planned critical

path of a project by pruning critical path activities, by 'fast tracking' (i.e., performing more activities

in parallel), and/or by 'crashing the critical

path' (i.e., shortening the durations of critical path activities by adding resources).

Answer option A is incorrect. ABEHJ takes only 22 days to complete.

ABEHJ= A(4)+B(5)+E(2)+H(7)+J(4)= 22

Answer option C is incorrect. ABDHJ takes 21 days to complete.

ABDHJ= A(4)+B(5)+D(1)+H(7)+J(4)= 21

Answer option B is incorrect. ABDIJ takes 21 days to complete.

ABDIJ= A(4)+B(5)+D(1)+I(7)+J(4)= 21


Page:    1 / 14   
Total 326 questions