PMI Project Management Professional (2023) Exam Practice Test

Page: 1 / 14
Total 588 questions
Question 1

A company plans to initiate a project involving a new technology. Approval for the project is required. What should the project manager do?



Answer : C

Question 2

A project manager is leading an engineering project. The project manager must obtain some certifications before mass production, which is scheduled in 3 months. The certification process will require at least 6 months.

What should the project manager do next?



Answer : D

Question 3

The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path.

What should the project manager do in this situation?



Answer : C

Question 4

An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a call from the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available. This is going to significantly impact the deliverable.

What should the project manager do?



Answer : A

Question 5

A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the different requirements?



Answer : C

Question 6

During an iteration review session, some product features are at risk of being canceled due to high operational costs when the product is launched into a production environment. What type of analysis should the project lead have conducted to avoid this situation?



Answer : B

Question 7

During project implementation, one team finds out that a key project deliverable was not budgeted. What should the project manager do first?



Answer : B

Page:    1 / 14   
Total 588 questions