PRINCE2 7 Foundation written PRINCE2-7-Foundation Exam Questions

Page: 1 / 14
Total 463 questions
Question 1

Which is a purpose of a Project Brief?



Answer : D

The purpose of a Project Brief in PRINCE2 is to provide a solid basis for the initiation of the project. The Project Brief includes the outline of the project's objectives, scope, constraints, and assumptions. It is developed during the 'Starting up a Project' process and is used to ensure that a clear, concise, and feasible plan is proposed before the project is formally initiated. Reference: PRINCE2 7 Foundation resources and materials.


Question 2

According to the 'exception management' technique, when should the team manager raise an issue?



Answer : C

According to the 'exception management' technique, the team manager should raise an issue when they predict that a product will cause a work package to exceed its time tolerance. This proactive approach allows for timely decision-making and corrective action by the Project Board, ensuring that project delivery is kept on track and within the agreed tolerances. Reference: PRINCE2 methodology and exception management guidance.


Question 3

Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?



Answer : D

The PRINCE2 principle of 'Defined roles and responsibilities' is crucial because it establishes a clear understanding of who is involved in the project and what each member of the team is expected to do. This clarity ensures that everyone knows their specific responsibilities, contributing to effective project governance and smooth execution. Reference: PRINCE2 7 Foundation Handbook and official training materials.


Question 4

What must be done for a project to be a PRINCE2 project?



Answer : B

For a project to be considered a PRINCE2 project, it must meet the minimum requirements for applying the seven PRINCE2 themes. These themes (Business Case, Organization, Quality, Plans, Risk, Change, and Progress) provide a framework for managing the project and ensuring that it is conducted in a systematic, consistent manner that is aligned with PRINCE2 principles. Reference: = PRINCE2 7 Foundation handbook and online resources


Question 5

What is performed as part of the recommended risk management procedure?



Answer : B

As part of the recommended risk management procedure in PRINCE2, it is essential to regularly review risk management practices to ensure their effectiveness. This involves evaluating how risks are identified, assessed, and controlled throughout the project lifecycle. Reference: PRINCE2 Foundation Handbook, Risk Management section.


Question 6

In which process are the key decisions to control the project made?



Answer : A

In PRINCE2, the 'Directing a Project' process is where the key decisions to control the overall project are made. This process involves the Project Board and is crucial for providing overall direction and management oversight throughout the lifecycle of the project, including key decision points such as project initiation, stage boundaries, and project closure. Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation


Question 7

Which describes a risk effect?



Answer : C

The risk effect in PRINCE2 describes the potential impact on project objectives if a specific threat or opportunity were to occur. This understanding is crucial in assessing the significance of the risk and determining the appropriate management response. Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.


Page:    1 / 14   
Total 463 questions