PRINCE2-Agile-Foundation PRINCE2 Agile Foundation Exam Practice Test

Page: 1 / 14
Total 92 questions
Question 1

How does agile address the risk associated with the project not being fully understood at the beginning?



Answer : D


Question 2

Which is a purpose of the 'controlling stage' process?



Answer : C


%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control

Question 3

Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?



Answer : A


Question 4

Which statement explains the PRINCE2 Agile behavior of 'exploration'?



Answer : D


Question 5

When tailoring the plans theme in an agile environment, what is recommended about using a Gantt chart?



Answer : B


Question 6

Which should be an objective of a retrospective?



Answer : B


Question 7

Why is Lean Startup included in the 'starting up a project' process in PRINCE2 Agile?



Answer : C


Page:    1 / 14   
Total 92 questions