PRINCE2-Agile-Foundation PRINCE2 Agile Foundation Exam Practice Test

Page: 1 / 14
Total 92 questions
Question 1

Which statement about quality tolerances for a product is CORRECT in an agile context?



Answer : C


Question 2

Which statement BEST describes the PRINCE2 Agile guidance for change?



Answer : A


Question 3

Which well-known agile method uses visualization, and controls work in progress?



Answer : D


Question 4

In Lean Startup, what is based on the concept of 'learn the most with the least effort'?



Answer : B


Question 5

Which is an advantage of frequent releases?



Answer : D


Question 6

Why are team working agreement produced?



Answer : B

Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true


Question 7

When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?



Answer : C


Page:    1 / 14   
Total 92 questions