PRINCE2-Agile-Foundation PRINCE2 Agile Foundation Exam Practice Test

Page: 1 / 14
Total 50 questions

Question 1

When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?



Answer : C

Question 2

Why are team working agreement produced?



Answer : B

Question 3

What should be decided when configuring PRINCE2 effectively?



Answer : C

Question 4

Which two statements are key responsibilities of supplier representative?

1. They highlight areas that the project may impact from a technical perspective.

2. They are partially assigned to the delivery team.

3. They create the project's specialist products.

4. They prioritize requirements.



Answer : D

Question 5

Which statement about the 'embrace change' target is CORRECT?



Answer : D

Page:    1 / 14   
Total 50 questions