PRINCE2-Foundation PRINCE 2 Foundation Exam Practice Test

Page: 1 / 14
Total 341 questions
Question 1

Which statement describes the context of the 'initiating a project" process?



Answer : B


Question 2

What should be implemented using a risk budget?

1. A request for change

2. A contingent plan

3. Actions to avoid a risk from occurring

4. Responses to dis-benefits



Answer : A


Question 3

Which statement about the length of management stages in a project is CORRECT?



Answer : C


Question 4

Which is a minimum requirement for applying the quality theme?



Answer : A


Question 5

Which is a purpose of a quality register?



Answer : B


Question 6

According to the 'defined roles and responsibilities' principle, how many categories of stakeholder interest need to be represented in the project management team?



Answer : C


Question 7

What process provides information on a team's work to the project manager?



Answer : D


Page:    1 / 14   
Total 341 questions