In which of the following do you use a work item in Focused Build?
Answer : C
C is correct because in Focused Build, you use a work item in sprints. A work item is a document that describes a configuration requirement or gap for a scope item. A work item is assigned to a sprint, which is a time-boxed iteration where the work item is implemented and tested by the Scrum team. Verified :
Which task should you include in your procedure while preparing for a fit-to-standard analysis in an SAP Data Warehouse Cloud project?Note: There are 2 correct answers to this question.
What is the objective of a sprint retrospective meeting?
Answer : A
A is correct because improving the Scrum process is the objective of a sprint retrospective meeting. The sprint retrospective meeting is a time for the Scrum Team to reflect on how they worked together in the last sprint and identify ways to enhance their effectiveness and efficiency. Verified :
:What is a Sprint Retrospective? | Scrum.org
You are defining the testing strategy for your project.What would you include in a Scope of Integration test?
Answer : A
A is correct because the functionality of end-to-end business processes is one of the things that you would include in a Scope of Integration test. The integration test is a test that verifies that the solution works as expected across different systems and interfaces, and supports the complete business scenarios that are relevant for the customer. Verified :
: SAP Activate Project Management Certification Guide, page 120
In which phase will the customer develop a preliminary strategy for building a target Operations and Support organizational model?
Answer : C
C is correct because in the Prepare phase, the customer will develop a preliminary strategy for building a target Operations and Support organizational model. The Operations and Support organizational model is a structure that defines the roles, responsibilities, processes, and tools for operating and supporting the solution after go-live. The preliminary strategy helps to identify the current and future state of the model, as well as the gaps and actions that need to be addressed.
According to the Definition of Done, which activity must be completed for each Sprint?
Answer : B
B is correct because according to the Definition of Done, the solution must be built and configured in the development system (DEV) for each Sprint. This means that all user stories in the Sprint backlog must be completed, tested, and accepted by the product owner in the DEV system before moving to the next Sprint. Verified :
:SAP Activate Project Management Certification Guide, page 114
When performing an SAP Readiness Check in system conversion, what areas are covered within the result?Note: There are 3 correct answers to this question
Answer : A, C, E
A is correct because SAP Readiness Check in system conversion covers the area of recommended SAP Fiori apps, which are apps that are suggested by SAP based on the customer's current usage of SAP GUI transactions.
C is correct because SAP Readiness Check in system conversion covers the area of sizing for SAP S/4HANA, which is an estimation of the hardware and software resources required to run SAP S/4HANA based on the customer's current system data.
E is correct because SAP Readiness Check in system conversion covers the area of simplification database, which is a collection of simplification items that describe the changes and adaptations required for SAP S/4HANA compared to the previous SAP ERP releases. Verified :
: SAP Readiness Check 2.0 for SAP S/4HANA