SAP C_S43_2022 SAP Certified Associate - SAP S/4HANA Asset Management Exam Practice Test

Page: 1 / 14
Total 80 questions
Question 1

Which objects can you assign to a Maintenance Service Order Item? Note: There are 2 correct answers to this question.



Answer : A, B


Question 2

How does the work center influence cost calculation in the maintenance order? Note: There are 2 correct answers to this question



Answer : B, D

The work center influences cost calculation in the maintenance order via the cost center and activity type, and via the activity type and hourly rate. The cost center and activity type are assigned to the work center in the master data, and they determine the planned costs of the work center. The activity type and hourly rate are used to calculate the actual costs of the work center based on the actual hours reported for the maintenance order operations.

Option A (Via cost center assigned to a personnel number) is incorrect, because the cost center assigned to a personnel number is not relevant for the cost calculation of the work center. Option C (Via organizational unit and personal hourly rate) is also incorrect, because the organizational unit and personal hourly rate are not used to calculate the costs of the work center.

References:

Cost Centers and Activity Types

Work Center Utilization


Question 3

What are characteristics of the structure indicator? Note: There are 2 correct answers to this question



Question 4

Which objects have been enhanced with linear data in maintenance processes? Note: There are 3 correct answers to this question



Question 5

Which of the following is a prerequisite for external refurbishment?



Answer : D

External refurbishment is the process of sending defective or worn-out spare parts to an external vendor for repair or replacement. To carry out this process, you need to create a maintenance order with an external operation that has the subcontracting indicator activated. This indicator allows you to create a purchase requisition and a purchase order for the external service. The external operation also requires an external work center, a control key, and a material component with the valuation type of the defective part. The order type for external refurbishment is not a prerequisite, but a configuration option that can be used to differentiate the process from internal refurbishment. The material group for externally refurbished materials is not relevant for the process, as the material master data is not changed by the refurbishment. The assignment of an external work center to a maintenance order operation is necessary, but not sufficient, for external refurbishment. You also need to activate the subcontracting indicator in the external activity.References:

Explaining Refurbishment of Spare Parts, section ''Refurbishing Spare Parts Externally''

Refurbishment of Repairable Spares: Integration between SAP-PM and SAP-MM, section ''4.2 External Refurbishment: Major Steps''


Question 6

You want to set up a general maintenance task list for inspection rounds using the overall time confirmation as a simplified way to record measurement documents. What do you need to do? Note: There are 2 correct answers to this question



Answer : A, B

To set up a general maintenance task list for inspection rounds using the overall time confirmation as a simplified way to record measurement documents, you need to do the following steps:

Assign a piece of equipment with an allocated measuring point to a task list operation. This will allow you to inspect the equipment and record the measurement readings for the measuring point during the inspection round.You can assign the equipment either manually or automatically using the object list in the task list header1.

Assign a measuring point as a production resources/tools (PRT) to a task list operation. This will allow you to inspect the measuring point and record the measurement readings for it during the inspection round.You can assign the measuring point either manually or automatically using the PRT category 0010 (Measuring Point) in the task list operation1.

You do not need to assign an inspection lot to the task list header, as this is not required for inspection rounds.Inspection lots are used for quality inspections that are triggered by events such as goods receipt, production order, or sales order2.

You do not need to assign an inspection document as a PRT to the task list operation, as this is not supported for inspection rounds.Inspection documents are used for quality inspections that are based on inspection plans and inspection characteristics2.References:PM - General maintenance task listandSet up your SAP S/4HANA system for EAM Inspection Checklistsin SAP Help Portal.


Question 7

During the implementation project you need to define the organizational units relevant for Plant Maintenance. Which of the following objects can you directly assign to a maintenance plant? Note: There are 2 correct answers to this question



Answer : A, D

A maintenance plant is the organizational unit in which the technical objects to be maintained are physically present. A maintenance plant can be directly assigned to the following objects:

A maintenance work center, which is a location where maintenance tasks are performed. A maintenance work center can be a person, a group of persons, or a technical object, such as a machine or a vehicle.A maintenance work center is defined by its capacity, availability, and cost rates1

A storage location, which is a place where spare parts and materials are stored within a plant. A storage location can be a warehouse, a bin, or a shelf.A storage location is defined by its address, stock type, and valuation area2

The other options are incorrect because:

A maintenance planner group, which is a group of planners who are responsible for planning maintenance activities in a maintenance planning plant. A maintenance planner group is not directly assigned to a maintenance plant, but to a maintenance planning plant.A maintenance planning plant is the organizational unit in which maintenance requirements are planned3

An organizational unit, which is a generic term for any unit of an organization that performs a specific function or task. An organizational unit can be a company code, a plant, a sales organization, a purchasing organization, etc. An organizational unit is not directly assigned to a maintenance plant, but to a higher-level organizational unit, such as a company code or a controlling area.

References:1: Maintenance Work Center | SAP Help Portal2: Storage Location | SAP Help Portal3: Maintenance Planner Group | SAP Help Portal : Organizational Unit | SAP Help Portal


Page:    1 / 14   
Total 80 questions