Which of the following parameters are available when you define a new maintenance plan category? Note: There are 3 correct answers to this question.
Answer : A, C, D
Which scheduling parameters are used in a multiple-counter plan? Note: There are 2 correct answers to this question.
Answer : A, B
What do you have to consider when planning maintenance work that is to be carried out by an external company?
Answer : C, D
When planning maintenance work that is to be carried out by an external company, you have to consider the following aspects:
If you assign a control key with indicator ''Service'' for an external service, you have to enter the actual values via the service entry sheet. This is because the service entry sheet is used to record the services performed by the external company and to verify the invoice. The service entry sheet is linked to the purchase order and the maintenance order operation.
For the maintenance order type, you have to assign the Enhanced Procurement Mode. This is because the Enhanced Procurement Mode enables you to use lean services and enhanced limits for external services. Lean services are intended for the procurement of small or highly specialized services that are carried out by external suppliers as part of an internal or external operation. They can be maintained in the material master as service products. Enhanced limits allow you to define a maximum amount for the external service without specifying the service specifications in advance.
If you assign a control key for an external order operation, the actual values must always be entered as a goods receipt in the system. This is not true, because the goods receipt is only required for external materials, not for external services. For external services, the service entry sheet is used instead.
Which steps are available for the maintenance technician when using the Report Malfunction bile? Note: There are 3 correct answers to this question.
Answer : B, C, D
The Report Malfunction app allows the maintenance technician to perform the following steps when reporting a malfunction of a technical object:
The Report Malfunction app does not allow the maintenance technician to perform the following steps when reporting a malfunction of a technical object:
What is characteristic for a maintenance order with status REL- if you also consider the capabilities of business functions? Note: There are 3 correct answers to this question.
Answer : A, B, E
A maintenance order with status REL means that the order is released and ready for execution. At this stage, the following characteristics apply:
Which operations can the responsible person perform after a maintenance order is technically completed? Note: There are 2 correct answers to this question
Answer : A, C
Lock or unlock the order: This prevents or allows further changes to the order data, such as actual costs, settlement rule, or confirmation data.
Change the settlement rule: This allows the responsible person to adjust the distribution of costs to the relevant receivers, such as cost centers, assets, or orders.
Post goods movements: This allows the responsible person to record the consumption or return of materials that were used for the maintenance work.
Enter measurement documents: This allows the responsible person to record the measurement readings of the technical objects that were maintained.
Update the estimated costs: This is only possible before the order is released or during the execution phase.
Change the planned costs: This is only possible before the order is released or during the execution phase.
Change the order type: This is only possible before the order is released.
Change the order status: This is only possible before the order is technically completed or after it is reversed.
Therefore, the correct answers are A and C.References:1: Maintenance Order Types | SAP Help Portal
The planner adds non-stock material in a released maintenance order. What are possible options within the maintenance order? Note: There are 3 correct answers to this question?
Answer : A, B, C
Among the given options, the following are possible for non-stock materials in a released maintenance order:
The following options are not possible for non-stock materials in a released maintenance order: