Based on the SAP Activate methodology; which activities must you perform in the Explore phase? Note: There are 2 correct answers to this question.
How is the productive system configured?
Note: There are 2 correct answers to this question.
Answer : A, C
The productive system is configured through transports from the quality system and through Central Business Configuration (CBC) in SAP Business Technology Platform. Transports are used to transfer the configuration settings from the quality system to the productive system. CBC is used to configure additional settings that are specific to the productive system, such as company code, plant, sales organization, etc. Reference: SAP Help Portal - Configuring Your Productive System
Which steps are required for data load preparation? There are 3 correct answers to this question.
What are the steps for conducting automated business process testing" Note: There are 3 correct answers to this question.
In a preventive maintenance process, a maintenance planner and a maintenance technician are involved. Which process steps are part of the maintenance planner's tasks? Note: There are 3 correct answers to this question.
Answer : A, C, D
The process steps that are part of the maintenance planner's tasks in a preventive maintenance process are:
Create the maintenance plan. This is the step where the maintenance planner defines the technical object, the maintenance strategy, the maintenance cycle, and the scheduling parameters for the preventive maintenance process.
Release the preventive maintenance order. This is the step where the maintenance planner releases the order that is generated from the maintenance plan according to the schedule. Releasing the order means that it is ready for execution and confirmation.
Technically complete the preventive maintenance order. This is the step where the maintenance planner sets the status of the order to technically completed after all the operations and suboperations have been confirmed. Technically completing the order means that no further work is required and that it can be settled and archived. Reference: [SAP Help Portal - Preventive Maintenance Process]
When scheduling the maintenance plan, which call objects can be generated automatically? Note: There are 2 correct answers to this question.
Which technology is used to integrate SAP S/4HANA Cloud with other SAP and non-SAP applications?