SAP Certified Associate - Implementation Consultant - SAP S/4HANA Cloud Public Edition, Management Accounting C_S4CCO_2506 Exam Questions

Page: 1 / 14
Total 80 questions
Question 1

You have just performed the final goods issue and final activity confirmation for a production order.What are the implications in accounting? Note: There are 3 Correct Answe rs to this questio n.



Answer : B, C, E

Solution:

Here are the implications in accounting after you post the final goods issue and final activity confirmation for a production order, according to SAP documentation on learning.sap.com:

Correct Answe rs

* B. Increased direct material costs

The final goods issue posts the remaining raw materials to the order, increasing direct material costs. SAP Community+13SAP Learning+13SAP Learning+13

* C. Increased work in progress (WIP) costs

As material and production costs increase, WIP is immediately updated to reflect the value of ongoing production. SAP Learning+1SAP Learning+1

* E. Increased overhead costs

Overhead is recalculated based on the increased direct costs and posted to the order during these final production events. +14SAP Learning+14SAP Learning+14

Not Correct

* A. Increased variance costs -- These are not posted at this stage; variances are calculated later during the final goods receipt and settlement process.

* D. Decreased direct production costs -- Direct production costs actually increase due to the confirmation of final activities.

Final Selection:

* B. Increased direct material costs

* C. Increased work in progress (WIP) costs

* E. Increased overhead costs


Question 2

Which of the following are captured in a completed Digital Discovery Assessment?Note: There are 2 Correct Answe rs to this questio n.



Answer : A, D

Solution:

Here are the two elements captured in a completed Digital Discovery Assessment, based on learning.sap.com:

Correct Answe rs

A . Target customer go-live date

* During the Detailed Discovery phase of the DDA, project and scope questions are completed---including the customer's target go-live date---as part of the decision-making and handover information. Passquestio n.com+15learning.sap.com+15learning.sap.com+15

D . Known integration requirements

* The DDA captures known integrations (systems the customer plans to connect), ensuring these are included in the implementation scope handed over to the team. learning.sap.com+3learning.sap.com+3quizlet.com+3

Incorrect Options

* B. SAP Fiori application extensions are not part of the DDA---they're uncovered later during Fit-to-Standard.

* C. Business role permission requirements aren't captured in the DDA; these are scoped during realization or workshop phases.

Final Selection:

* A. Target customer go-live date

* D. Known integration requirements


Question 3

Which activities can you complete in the Maintain Business Roles SAP Fiori app?Note: There are 2 Correct Answe rs to this question,



Answer : A, C

Solution:

Based on learning.sap.com information about the Maintain Business Roles SAP Fiori app in SAP S/4HANA Cloud Public Edition, here are the two correct activities:

Correct Answe rs

A . Assign business catalogs to a business role

You can add one or more SAP Fiori business catalogs to a business role, which defines the apps and tiles that users assigned this role can access help.sap.com+7learning.sap.com+7learning.sap.com+7.

C . Maintain restrictions

The app allows administrators to set restrictions at the catalog level---such as limiting display types or data access for specific apps---directly within the business role definition learning.sap.com.

Incorrect Options

* B. Assign PFCG profiles to a business role -- This app doesn't link business roles to PFCG security profiles; that happens behind the scenes in the authorization layer.

* D. Maintain technical catalogs -- The app is designed for business catalogs and restrictions, not for managing technical catalogs.

Final Answe rs:

* A. Assign business catalogs to a business role

* C. Maintain restrictions


Question 4

You have just confirmed intermediate activities for a production order.Which are the consequences in event-based ? Note: There are 3 Correct Answe rs to this questio n.



Answer : B, C, E

Solution:

Based strictly on learning.sap.com documentation about event-based , after confirming intermediate activities for a production order, the following are the consequences:

Correct Answe rs

B . Overhead costs are calculated and posted to the order

Event-based overhead is triggered immediately after activity confirmations, calculating and posting overhead

costs to the production order based on direct material and activity costs learning.sap.com+6learning.sap.com+6learning.sap.com+6.

C . Work in progress (WIP) is calculated and posted

With each activity confirmation, WIP is recalculated based on target costs, and corresponding WIP posting is made against the production order community.sap.com+3learning.sap.com+3learning.sap.com+3.

E . Direct production costs are posted to the order through direct activity allocation

Activity confirmations allocate labor/machine time directly as costs to the order via internal activity allocation community.sap.com+5learning.sap.com+5learning.sap.com+5.

Not Correct

* A. Order settlement --- This does not occur immediately after activity confirmation; it occurs at goods receipt or final delivery.

* D. Variances are calculated and posted --- Variance calculation only occurs upon final goods receipt or delivery, not after intermediate activity confirmations.

Final Answe rs:

* B. Overhead costs are calculated and posted to the order

* C. Work in progress (WIP) is calculated and posted

* E. Direct production costs are posted to the order through direct activity allocation


Question 5

Which account types enable the derivation of attributed profitability segments? Note: There are 2 Correct Answe rs to this questio n.



Answer : B, D

Based strictly on learning.sap.com, the G/L account types that allow the derivation of attributed profitability segments are:

Correct Answe rs

* B. Primary costs or revenue

G/L accounts assigned to primary costs or primary revenue support automatic determination of attributed profitability segments during posting. learning.sap.com+15learning.sap.com+15learning.sap.com+15

* D. Secondary costs

G/L accounts assigned to secondary costs also support attribution of profitability segments. help.sap.com+3learning.sap.com+3learning.sap.com+3help.sap.com

Incorrect Options

* A. Balance sheet accounts with open item management --- Attributed profitability segments are not

derived from these accounts.

* C. Non-operating income --- These are typically held as balance sheet or non-CO-PA categories and do not

support attributed assignments.

Final Answe rs:

* B. Primary costs or revenue

* D. Secondary costs


Question 6

In a make-to-order business scenario with manufacturing, how does event-based revenue recognition ensure that COGS are always aligned with revenues?



Answer : A

Based solely on learning.sap.com, the correct answer to ''Which option ensures COGS are aligned with revenue in a make-to-order scenario using event-based revenue recognition?'' is:

A. At goods issue, COGS and revenue are recognized.

Here's why:

* In event-based revenue recognition (EBRR), when you post a goods issue tied to delivery, the system simultaneously recognizes both revenue and COGS in real time, based on predefined posting rules. This ensures real-time alignment between cost and revenue. learning.sap.com+6help.sap.com+6linkedin.com+6

No other delivery event---like billing or proof of delivery---provides this immediate alignment:

* Billing moves and clears billing-related entries later.

* Proof of delivery doesn't automatically trigger combined cost and revenue postings.

Final Answer:

* A. At goods issue, COGS and revenue are recognized


Question 7

What is the correct release code for the second feature delivery in February 2025?



Answer : C

According to the SAP S/4HANA Cloud release naming convention detailed on learning.sap.com, the code is structured as:

* YYMM, where YY = last two digits of the year, and MM = month of major release.

* Feature packages are numbered .1 or .2 based on their sequence (first or second delivery) within that cycle. learning.sap.com+8assets.dm.ux.sap.com+8learning.sap.com+8

For February 2025, the major release is ''2502'', and since this is the second feature delivery (the .2), the correct code is:

C. 2502.2

Introduction to Cloud Computing and SAP Cloud ERP Deployment Options


Page:    1 / 14   
Total 80 questions