How do you derive the hierarchy of a work breakdown structure from the numbers of their WBS elements?
Please choose the correct answer.
Response:
Answer : B
Which of the following items can be included in the planned costs for an activity besides the cost of the activity?
There are 3 correct answers to this question.
Response:
Answer : A, B, C
What are the prerequisites for automatic requirements grouping on the top WBS element of a project?
There are 2 correct answers to this question.
Response:
Answer : B, C
Which combination allows you to assign the material components in one WBS element to different grouping WBS element?
There are 2 correct answers to this question.
Response:
Answer : A, B, D
What are the three areas of the project screen?
There are 3 correct answers to this question.
Response:
Answer : A, B, D
In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity.
How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?
Please choose the correct answer.
Response:
Answer : B
Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships?
Please choose the correct answer.
Response:
Answer : B