SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Exam Practice Test

Page: 1 / 14
Total 165 questions
Question 1

Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity?

Please choose the correct answer.

Response:

Capacity planning board



Answer : B


Question 2

Which type of order is created at BOM level to cover requirements when a material shortage occurs in material planning?

Please choose the correct answer.

Response:



Answer : C


Question 3

Externally processed activities give rise to planned costs that are equivalent to the prices of the following?

There are 2 correct answers to this question.

Response:



Answer : A, B


Question 4

What are the various transactions in SAP PS with which a work breakdown structure can be created?

There are 3 correct answers to this question.

Response:



Answer : A, C, D


Question 5

When using budgeting and active availability control, which business transactions affect the current budget?

There are 3 correct answers to this question.

Response:



Answer : B, D, E


Question 6

Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the execution phase you have an option to set the actual dates in the sameway in the project planning board.

What is the status that must be set before you can enter actual start and actual end dates?

There are 2 correct answers to this question.

Response:



Answer : A, B


Question 7

What are the various elements that are included in checking rules?

There are 3 correct answers to this question.

Response:



Answer : A, B, C


Page:    1 / 14   
Total 165 questions