SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Exam Questions

Page: 1 / 14
Total 165 questions
Question 1

How do you derive the hierarchy of a work breakdown structure from the numbers of their WBS elements?

Please choose the correct answer.

Response:



Answer : B


Question 2

Which of the following items can be included in the planned costs for an activity besides the cost of the activity?

There are 3 correct answers to this question.

Response:



Answer : A, B, C


Question 3

What are the prerequisites for automatic requirements grouping on the top WBS element of a project?

There are 2 correct answers to this question.

Response:



Answer : B, C


Question 4

Which combination allows you to assign the material components in one WBS element to different grouping WBS element?

There are 2 correct answers to this question.

Response:



Answer : A, B, D


Question 5

What are the three areas of the project screen?

There are 3 correct answers to this question.

Response:



Answer : A, B, D


Question 6

In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity.

How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?

Please choose the correct answer.

Response:



Answer : B


Question 7

Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships?

Please choose the correct answer.

Response:



Answer : B


Page:    1 / 14   
Total 165 questions