SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Exam Questions

Page: 1 / 14
Total 165 questions
Question 1

In which type of project stock G/L account determination for project stock is controlled differently from collective stock using specific valuation classes for sales order stock and project stock in the material master?

There are 2 correct answers to this question.

Response:



Answer : A, C


Question 2

What are the different types of assembly orders that can be created?

There are 3 correct answers to this question.

Response:



Answer : B, C, D


Question 3

What are the two basic elements that SAP Project system provides for mapping the structures of projects?

There are 2 correct answers to this question.

Response:



Answer : A, D


Question 4

In your project, you choose internal activities to confirm actual dates. After you partially confirmed an internal activity, you want that the actual start will be considered for the calculation of the earliest scheduled dates.How can you implement this? Please choose the correct answer.

Response:



Answer : B


Question 5

What are the different views available for capacity planning and work center planning?

There are 2 correct answers to this question.

Response:



Answer : A, D


Question 6

Items procured through which of the following methods are not assigned to a stock segment and do not pass through a warehouse?

Please choose the correct answer.

Response:



Answer : C


Question 7

Consider a scenario where you have started by displaying the planned costs for the entire project and how these planned costs are distributed among the various value categories for WBS element WBS 2.

You then want to analyze the planned costs of WBS element WBS 2 for value category 620 according to cost distribution to the various periods.

Which type of reporting allows you to achieve this?

Please choose the correct answer.

Response:



Answer : A


Page:    1 / 14   
Total 165 questions