SAP C_TS422_2021 SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing 2021 Exam Practice Test

Page: 1 / 14
Total 82 questions
Question 1

Your production planners must execute planning only for specific resources. How can you achive this in advanced Planning(PP/DS)



Answer : A


Question 2

The MRP run detected a shortage of a materila that you sorce from an external supplier in full pallets. How can you make sure you will only recive full pallets?



Answer : A


Question 3

What do you use to dispatch operations from planned orders so that the production plan can be fulfilled?



Answer : A


Question 4

What are the consequences when you assgn a planned order to a production line manually, using the planning table in repetitive manufacturing?



Answer : D


Question 5

Your proyect team decides to use a make-to-order planning strategy for strategic in discrete manufacturing. What is the impact of this decision?



Answer : A, B, D


Question 6

What are some uses for the low-level code assigned to each material?



Answer : A, B


Question 7

You want to use capacity availability checks for production orders. Which settings have to be made for this?



Answer : C, D


Page:    1 / 14   
Total 82 questions