SAP C_TS422_2022 SAP Certified Associate - SAP S/4HANA Production Planning and Manufacturing Exam Practice Test

Page: 1 / 14
Total 80 questions
Question 1

For production orders, cost object controlling (COC) can be carried out on an order-related or product- related basis. Which of the following do you have to consider?

Note: There are 2 correct answers to this question.



Answer : A, B


Question 2

Where do you maintain data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.



Answer : A, B


Question 3

Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HAN



Answer : C


Question 4

What could be the reason for multiple commitments, where several operations have the same scheduled dates on a work center after dispatching?

Note: There are 2 correct answers to this question.



Answer : A, B


Question 5

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question



Answer : A, C


Question 6

You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?



Answer : B


Question 7

Your project uses process orders for the production of liquid chemicals. What can you define to ensure that production flow only happens in suitable and physically connected tanks? Note: There are 2 correct answers to this question.



Answer : B, C


Page:    1 / 14   
Total 80 questions