SAP C_TS422_2020 SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Exam Practice Test

Page:    1 / 14   
Total 80 questions

Question 1

Where does the system check master data selection settings during the creation of planned orders and production orders? Note: There are 3 correct answers to this question.



Answer : B, C, E

Question 2

Your company produces a finished good based on a forecast and expects it to being stock when customers order it. If customers order more than the forecasted quantity, the production quantity should be increased to try to meet the extra demand. Which planning strategy do you use?



Answer : D

Question 3

What are some uses for the low-level code assigned to each material? Note: There are 2 correct answers to this question.



Answer : A, C

Question 4

Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.



Answer : C, D

Question 5

What determines whether the planned independent requirements in MRP consume other requirements?



Answer : A

Page:    1 / 14   
Total 80 questions