SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing C_TS422_2504 Exam Questions

Page: 1 / 14
Total 87 questions
Question 1

What is a prerequisite for consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?



Answer : D


Question 2

You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do?

Note: There are 2 correct answers to this question.



Answer : B, C


Question 3

Which of the following would you recommend as SAP's strategic Sales and Operations planning tool?



Answer : B


Question 4

What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.



Answer : C, D


Question 5

Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.



Answer : A, C, E


Question 6

What are some benefits of planning with planned independent requirements for finished materials? Note: There are 2 correct answers to this question.



Answer : A, B


Question 7

How can you support a GMP (Good Manufacturing Practice) compliant production process? Note: There are 3 correct answers to this question.



Answer : A, C, E


Page:    1 / 14   
Total 87 questions