SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing C_TS422_2504 Exam Practice Test

Page: 1 / 14
Total 87 questions
Question 1

What does the material type influence?

Note: There are 2 correct answers to this question.



Answer : A, C


Question 2

Which of the following processes lead to an entry in the MRP planning file? Note: There are 2 correct answers to this question.



Answer : C, D


Question 3

You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do?

Note: There are 2 correct answers to this question.



Answer : B, C


Question 4

Which planning strategies can you use in the capacity scheduling table?

Note: There are 2 correct answers to this question.



Answer : A, B


Question 5

Which operations are considered in the capacity scheduling table?

Note: There are 2 correct answers to this question.



Answer : A, B


Question 6

Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.



Answer : C, D


Question 7

You want to use capacity availability checks for production orders. Which settings have to be made for this?

Note: There are 2 correct answers to this question.



Answer : A, D


Page:    1 / 14   
Total 87 questions