After a material has been included in a NETCH material requirements planning run you change its BOM (bill of materials).
Which of the following planning file entries for this material are set by the system?
Answer : C
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used for scheduling? (Choose three.)
Answer : B, C, D
Which types of objects can be changed with Engineering Change Management (ECM)? (Choose three)
Answer : A, D, E
What do you have to consider regarding lot size procedures?
Answer : C
What could be a consequence of confirming an operation?
Answer : B
Where can you define the valid receivers for production order costs?
Answer : B
You have maintained planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a material. For the coming months, you have planned requirements with requirement type LSF (derived from main strategy 10). Now, you want to change the requirement type from LSF to VSF (in accordance with planning strategy 40, planning with final assembly) for requirements in the existing production plan.
Which of the following scenarios are applicable in this case? (Choose two)
Answer : A, D