Question 1

Which artifacts in the testing workstream are created within the realize phase for the "new implementation of SAP S/4HANA Cloud" transition path? There are 2 answers to this question.



Answer : B, D


Question 2

Which of the following are levels in the structure of an SAP Best practices solution package? There are 2 answers to this question.



Answer : B, C


Question 3

What does "de-coupling extensions" mean in SAP S/4HANA Cloud?



Answer : D


Question 4

There are several SAP options for creating data insights and providing summaries in a structured format for SAP customers, which of the following are part of the SAP Analytics and Reporting Portfolio?



Answer : A, B, C, D


Question 5

What is the difference between the "system conversion" and the "new implementation OF SAP S/4HANA transaction path.

There are 2 option to this question.



Answer : A, C


Question 6

In SAP Activate, what replaces the detailed Blueprint from ASAP? Please choose the answer.



Answer : A


Question 7

Which of the following belong to the application design and configuration workstream for SAP S/4HANA cloud in the explore phase?

There are 2 answers to this question.



Answer : A, D