You are performing an upgrade of an SAP ECC development system with SUM. What is the earliest point when the upgrade is considered complete and you can allow all dialog users to log on to the system?
Please choose the correct answer.
Response:
Answer : B
During a SUM run you want to check if the phase SHADOW_IMPORT_INC is still running properly. Where can you find information about this?
There are 2 correct answers to this question.
Response:
Answer : B, D
You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime.
The server provides 8 CPU cores. Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center you can see 40 Process Buckets being executed in parallel.
Why are 40 Process Buckets executed in parallel?
Please choose the correct answer.
Response:
Answer : D
In ICNV. How database operations synchronized between the source and the target table?
Answer : A
What do you do to prepare the database migration option of a SUM procedure?
There are 3 correct answers
Response:
Answer : B, C, D
You are planning to use DMO of SUM to perform an "inplace-migration" to SAP HAN
Answer : C, E
What is the benefit of using the file UPGANA.XML from a previous SUM run?
Please choose the correct answer.
Response:
Answer : B