Who can abnormally terminate a Sprint?
Answer : C
According to the Scrum Guide1, a Sprint can be cancelled before the Sprint time-box is over. Only the Product Owner has the authority to cancel the Sprint, although he or she may do so under influence from the stakeholders, the Developers, or the Scrum Master. A Sprint would be cancelled if the Sprint Goal becomes obsolete. This might occur if the company changes direction or if market or technology conditions change. In general, a Sprint should be cancelled if it no longer makes sense given the circumstances. But, due to the short duration of Sprints, cancellation rarely makes sense.
Who owns the Sprint Backlog?
Answer : D
Sprint Backlog is owned by the Development Team. The Scrum Guide states that ''the Sprint Backlog is the set of Product Backlog items selected for the Sprint, plus a plan for delivering the product Increment and realizing the Sprint Goal. ... The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog emerges during the Sprint. This emergence occurs as the Development Team works through the plan and learns more about the work needed to achieve the Sprint Goal.''
What does it mean to say that an event has a time-box?
Answer : D
According to the Scrum Guide1, each event in Scrum is a formal opportunity to inspect and adapt something. These events are specifically designed to enable critical transparency and inspection. Failure to include any of these events results in reduced transparency and is a lost opportunity to inspect and adapt. All events are time-boxed events, such that every event has a maximum duration. Once a Sprint begins, its duration is fixed and cannot be shortened or lengthened. The remaining events may end whenever the purpose of the event is achieved, ensuring an appropriate amount of time is spent without allowing waste in the process.
Who has the final say on the order of the Product Backlog?
Answer : B
According to the Scrum Guide, the Product Owner has the final say on the order of the Product Backlog, as he or she is responsible for maximizing the value of the product and the work of the Development Team. The other roles do not have this authority, although they may provide input and suggestions to the Product Owner.
Who should make sure everyone on the scrum Team does their tasks for the sprint? (choose the best answer)
Answer : D
According to the Scrum Guide, the Scrum Team should make sure that everyone on the team does their tasks for the Sprint, as they are collectively accountable for creating valuable Increments that meet stakeholder needs and expectations. The other options are not valid, as they imply that someone else outside the Scrum Team (such as a project manager) or another role on the Scrum Team (such as the Product Owner or the Scrum Master) is responsible for making sure that everyone does their tasks for the Sprint.
Which three of the following are time-boxed events in Scrum? (Choose three.)
Answer : C, D, G
According to the Scrum Guide1, each event in Scrum is a formal opportunity to inspect and adapt something. These events are specifically designed to enable critical transparency and inspection. Failure to include any of these events results in reduced transparency and is a lost opportunity to inspect and adapt. All events are time-boxed events, such that every event has a maximum duration. Once a Sprint begins, its duration is fixed and cannot be shortened or lengthened. The remaining events may end whenever the purpose of the event is achieved, ensuring an appropriate amount of time is spent without allowing waste in the process. The time-boxed events in Scrum are:
Sprint Planning (eight hours or less for a one-month Sprint)
Daily Scrum (15 minutes or less for a one-month Sprint)
Sprint Review (four hours or less for a one-month Sprint)
Sprint Retrospective (three hours or less for a one-month Sprint)
The other options are not time-boxed events in Scrum.
Which are characteristics of the Daily Scrum?
(choose the best two answers)
Answer : A, B
According to the Scrum Guide, two characteristics of the Daily Scrum are its location and time remain constant and its purpose is to inspect progress toward the Sprint Goal and adapt the Sprint Backlog. These characteristics promote consistency, transparency, and adaptation within the Development Team. The other options are not valid characteristics of the Daily Scrum, as they are either irrelevant (such as being held first thing in the morning) or inappropriate (such as being free form, facilitated by the team lead, or consisting of the Scrum Master asking for status).