Scrum Professional Scrum Master I PSM-I Exam Practice Test

Page: 1 / 14
Total 268 questions
Question 1

Who owns the Sprint Backlog?



Answer : D

Sprint Backlog is owned by the Development Team. The Scrum Guide states that ''the Sprint Backlog is the set of Product Backlog items selected for the Sprint, plus a plan for delivering the product Increment and realizing the Sprint Goal. ... The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog emerges during the Sprint. This emergence occurs as the Development Team works through the plan and learns more about the work needed to achieve the Sprint Goal.''


Question 2

Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?



Question 3

For which of the following is the Scrum Master responsible?

(choose the best answer)



Answer : A

According to the Scrum Guide, the Scrum Master is responsible for promoting and supporting Scrum as defined in the Scrum Guide1.Scrum Masters do this by helping everyone understand Scrum theory, practices, rules, and values1.The Scrum Master is accountable for establishing Scrum2.They do this by helping everyone understand Scrum theory and practice, both within the Scrum Team and the organization while serving the Scrum Team as well as the larger organization2.

Option B is incorrect because keeping track of resource allocation is not a responsibility of the Scrum Master. The Scrum Master does not manage or control the resources of the Scrum Team or the organization.The Scrum Team is self-organizing and responsible for managing its own work within a Sprint1.

Option C is incorrect because managing the performance of the Scrum Team is not a responsibility of the Scrum Master. The Scrum Master does not evaluate or appraise the performance of the Development Team or the Product Owner.The Scrum Master serves the Development Team by coaching them on self-organization and cross-functionality, and serves the Product Owner by ensuring that goals, scope, and product domain are understood by everyone on the Scrum Team1.

Option D is incorrect because the meetings and the objectives that a Scrum Team sets for itself are not a responsibility of the Scrum Master. The Scrum Master does not dictate or prescribe what meetings or objectives a Scrum Team should have.The Scrum Master facilitates the Scrum Events as requested or needed, and ensures that they are positive, productive, and kept within the time-box1.


Question 4

What are three ways Scrum promotes self-organization? (Choose three.)



Question 5

Scrum has a role called ''Project Manager''.



Answer : B

The correct answer is B, because there is no role called ''Project Manager'' in Scrum. The Scrum Guide states that ''Scrum recognizes no titles for Development Team members other than Developer, regardless of the work being performed by the person; there are no exceptions to this rule.'' Therefore, Scrum has only three roles: Product Owner, Scrum Master, and Developer.


Question 6

When does the next Sprint begin?



Answer : B

The next Sprint begins immediately after the conclusion of the previous Sprint, as stated in the Scrum Guide: ''Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint.''


Question 7

Who determines how work is performed during the Sprint?



Answer : B

The correct answer is B, because the Development Team determines how work is performed during the Sprint. The Scrum Guide states that ''development Teams are self-organizing. No one (not even the Scrum Master) tells the Development Team how to turn Product Backlog into Increments of potentially releasable functionality.'' Therefore, the Development Team has the autonomy and responsibility to organize and manage its own work.


Page:    1 / 14   
Total 268 questions