Scrum Professional Scrum Master I PSM-I Exam Questions

Page: 1 / 14
Total 268 questions
Question 1

What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? (Choose two.)



Answer : B, C

The correct answers are B and C, because these are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity. The Scrum Guide states that ''the Scrum Master serves the Development Team in several ways, including ... removing impediments to the Development Team's progress; facilitating Scrum events as requested or needed; and coaching the Development Team in self-organization and cross-functionality.'' Therefore, by removing impediments and facilitating decisions, the Scrum Master helps the Development Team focus on their work and deliver value.


Question 2
Question 3

Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the order teams. What should the Scrum Master do?



Question 4

When does the next Sprint begin?



Answer : B

The next Sprint begins immediately after the conclusion of the previous Sprint, as stated in the Scrum Guide: ''Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint.''


Question 5
Question 6

How much of the Sprint Backlog must be defined during the Sprint Planning event?



Answer : C

The correct answer is C, because the Scrum Guide states that ''the Development Team usually starts by designing the system and the work needed to convert the Product Backlog into a working product Increment. Work planned for the first days of the Sprint by the Development Team is decomposed by the end of this meeting, often to units of one day or less. The Development Team self-organizes to undertake the work in the Sprint Backlog, both during Sprint Planning and as needed throughout the Sprint.'' Therefore, enough work should be defined during the Sprint Planning event so that the Development Team can create its best forecast of what it can do, and to start the first several days of the Sprint.


Question 7
Page:    1 / 14   
Total 268 questions